Temporary Driveway Alignment Change at 564 Eglinton Avenue West for Chaplin Station

WHAT WORK IS TAKING PLACE?

Beginning January 22, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and existing the driveway.  A flag person will be on site to assist with entry and egress.

TIMING  Lire la suite »

janvier 12 2018

Overnight Monitoring Installations Around the TTC Eglinton West Station Bus Loop

WHAT WORK IS TAKING PLACE?

Geotechnical monitoring instruments are installed in the vicinity of the station construction to monitor the ground conditions as construction is underway. 

Monitoring instruments are regularly checked to measure any movements of the ground and assess if there is a need for additional measures. 

The majority of the monitors for Cedarvale Station were installed in late 2016/early 2017. Lire la suite »

janvier 10 2018

Overnight Sanitary Sewer Line Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are installing a new sanitary sewer system along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  As part of this work, diversion of the existing sanitary sewer service line is required on several occasions over the course of the work.  Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new sanitary sewer infrastructure is installed. Lire la suite »

janvier 08 2018
janvier 08 2018
janvier 08 2018

Traffic and Pedestrian Changes at Chaplin Station for Wet Utility Work

WHAT WORK IS TAKING PLACE?

As early as January 15, new construction staging and traffic and pedestrian changes will be implemented at Chaplin Station.  The southwest work zone will be extended south onto Chaplin Cres and the southeast work zone will be made smaller.

Wet utilities work, including watermain, storm and sanitary sewer installation and relocation, as well as support of excavation activities will occur during this stage.   Lire la suite »

janvier 05 2018

REPOST & UPDATE: Avenue Station Sewer Lining - East Sewer Section

Original Issue Date: October 14, 2017 (West Sewer Section info)
Repost & Update Date: November 15, 2017 (Avenue Rd Sewer Section info)
Repost & Update (2) Date: January 5, 2018 (East Sewer Section info)
Repost & Update (2) Date: January 15, 2018  (East Sewer Section - timing update)

  Lire la suite »

décembre 21 2017

Construction Notice - Forest Hill - Asphalt Work at Hilltop & Eglinton

WHAT WORK IS TAKING PLACE?

As part of the ongoing sewer work at Forest Hill Station, crews will be removing the road plates and asphalting.  While this work takes place, one lane of Eglinton Ave W will be closed in the vicinity of Eglinton Ave W between Hilltop Rd and Chiltern Hill Rd.

TIMING 

Thursday December 21, 2017

7:00 a.m. – 11:00 p.m.

WHAT TO EXPECT Lire la suite »

décembre 21 2017

Watermain Valve Installation at Avenue Station

WHAT WORK IS TAKING PLACE?

In early January, work will take place to install a valve on the watermain under the south side of Eglinton Avenue. This valve will allow for isolation of the section of the watermain between Avenue Road and Highbourne Road. The closest address to the location of the work is between 253 to 263 Eglinton Ave W.

WHAT TO EXPECT Lire la suite »

décembre 18 2017

Chaplin Station - Temporary Driveway Realignment at 564 Eglinton Avenue West

WHAT WORK IS TAKING PLACE?

Beginning December 18, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and exiting the driveway.  A flag person will be on site to assist with traffic flow.