octobre 112016

Subsurface Utility Engineering (SUE) Investigations at Cedarvale Station

What Work is Taking Place?

  • To prepare for future construction of Cedarvale Station, crews will be conducting Subsurface Utility Engineering (SUE) investigations along the shoulder of Allen Road North and South, north of Eglinton Avenue West.
  • Crews will drill bore holes and use a hydro-vacuum truck on the shoulder of the road to determine the location of the underground utilities and the ground conditions around the intersection for design purposes. 

Timing

  • Work is expected to begin the evening of October 12th and will take approximately two
octobre 112016

Geotechnical Instrumentation and Monitoring at Cedarvale Station

What Work is Taking Place?

  • Geotechnical instrumentation and monitoring is required for the protection of the existing buildings and underground utilities by monitoring movements of the ground, support of excavation, utilities, structures and groundwater regime, prior, during and following construction in order to assess the need for implementation of mitigation measures.
  • Crews will drill approximately 15+ boreholes in the Cedarvale Station area to install geotechnical instrumentation and monitoring equipment. 

Timing

septembre 132016
septembre 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Lire la suite »

août 192016

Decommissioning of Launch Shaft Site at Allen Road

Beginning in the mid-August, crews will be removing concrete surface pads and site facilities as part of the decommissioning of the Launch Shaft site at the northeast corner of Eglinton Avenue and Allen Road. Lire la suite »

juillet 072016

Park Hill Road Closure at Cedarvale Station

The closure of Park Hill Road was first communicated in a notice on April 19th 2016. This work had been delayed due to unforeseen circumstances. The closure of Park Hill Road will now proceed this month. The north-south pedestrian walkway along the Allen Road southbound will close at a future date. We apologize for any inconvenience. Lire la suite »

mai 172016

Cedarvale Station Open House

Thank you for attending our Cedarvale station open house on May 16, 2016. 

For those of you who missed it, the presentation is here: