Allen Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juillet 072016

Park Hill Road Closure at Cedarvale Station

The closure of Park Hill Road was first communicated in a notice on April 19th 2016. This work had been delayed due to unforeseen circumstances. The closure of Park Hill Road will now proceed this month. The north-south pedestrian walkway along the Allen Road southbound will close at a future date. We apologize for any inconvenience. Lire la suite »

mai 172016

Cedarvale Station Open House

Thank you for attending our Cedarvale station open house on May 16, 2016. 

For those of you who missed it, the presentation is here:

avril 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Lire la suite »

février 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Lire la suite »

janvier 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Lire la suite »