Avenue Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
janvier 052018

REPOST & UPDATE: Avenue Station Sewer Lining - East Sewer Section

Original Issue Date: October 14, 2017 (West Sewer Section info)
Repost & Update Date: November 15, 2017 (Avenue Rd Sewer Section info)
Repost & Update (2) Date: January 5, 2018 (East Sewer Section info)
Repost & Update (2) Date: January 15, 2018  (East Sewer Section - timing update)

  Lire la suite »

janvier 042018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on January 3, 2018. You can see the presentation here:

Lire la suite »

décembre 212017

Watermain Valve Installation at Avenue Station

WHAT WORK IS TAKING PLACE?

In early January, work will take place to install a valve on the watermain under the south side of Eglinton Avenue. This valve will allow for isolation of the section of the watermain between Avenue Road and Highbourne Road. The closest address to the location of the work is between 253 to 263 Eglinton Ave W.

WHAT TO EXPECT Lire la suite »

décembre 062017

Watermain Lining at Avenue Station Secondary Entrance

Original Issue Date: December 4, 2017
Updated: December 6, 2017
Updated: January 15, 2018 (timing)

 

WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

Properties 270 – 302 Eglinton Avenue West

WHAT WORK IS TAKING PLACE? Lire la suite »

novembre 162017

Gantry Crane Delivery and Installation at Avenue Station Secondary Entrance

What Work is Taking Place?

Beginning Wednesday November 22, a large overhead Gantry Crane will be delivered to Avenue Station and installed at the Secondary Entrance site.  

Several truckloads of large steel columns that the overhead crane will sit on will be delivered to the site.  Due to the size of these deliveries, trucks will be backed-in to the existing construction zone east of Avenue Road through the west gate.  Short traffic interruptions can be expected while these deliveries take place. Lire la suite »

novembre 152017

REPOST & UPDATE: Avenue Station Sewer Lining

Original Issue Date: October 14, 2017
Repost & Update Date: November 15, 2017

 

Beginning as early as November 20, 2017.

Sewer lining work takes place on a 24 hour schedule.

WHAT WORK IS TAKING PLACE? Lire la suite »