Cedarvale Station: Road Closures for Utility Relocation & Support of Excavation

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
juin 27, 2017

What Work is Taking Place?

In June 2017, the Cedarvale Station work zones are now in full swing as crews complete tunnel concrete pours, utility relocation, and support of excavation activities.

To continue to relocate and upgrade storm and sanitary sewer infrastructure and complete support of excavation, traffic changes in the vicinity of Cedarvale Station are required.

Throughout the Summer 2017, the following roads will be closed at Eglinton Avenue West:

  • Everden Road will close for approximately 6 – 8 months to complete sewer work and support of excavation
  • Winnett Avenue will close for approximately 1 month to complete sewer work
  • Please note, the timing of the Winnett and Everden closures may overlap.
  • Park Hill Road and Strathearn Road will remain closed.

A new work zone will be implemented on the south side of Eglinton Avenue West between Winnett Avenue and Strathearn Road. Traffic will be shifted on Eglinton Avenue West and changes to pedestrian crosswalks and walkways will be required. 

Access to driveways will be maintained throughout the work. Local access for residents will be maintained from Gloucester Grove.

Hours of Work

  • Work can be expected between the hours of 7:00 AM and 11:00 PM, 7 days a week.
    • Work outside these hours may be required for other construction activities. This information will be communicated separately. 
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect 

  • Nearby residents and businesses can expect noise in the area caused by loaders, trucks and other construction equipment, as well as dust from drilling activity and debris removal.
  • For safety purposes, metal fencing will be erected around the work zone, signage for traffic and public diversions, and there will be dust control measures in place.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

Please Contact Us

 If you would like more detail about this work or any other aspect of the Eglinton Crosstown project, please contact us at (416) 782-8118.

 

 

Thank you for your patience as we work to build this important project.

Please support your local businesses during construction.