Chaplin Crescent

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
janvier 102018

Overnight Sanitary Sewer Line Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are installing a new sanitary sewer system along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  As part of this work, diversion of the existing sanitary sewer service line is required on several occasions over the course of the work.  Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new sanitary sewer infrastructure is installed. Lire la suite »

janvier 082018

Traffic and Pedestrian Changes at Chaplin Station for Wet Utility Work

WHAT WORK IS TAKING PLACE?

As early as January 15, new construction staging and traffic and pedestrian changes will be implemented at Chaplin Station.  The southwest work zone will be extended south onto Chaplin Cres and the southeast work zone will be made smaller.

Wet utilities work, including watermain, storm and sanitary sewer installation and relocation, as well as support of excavation activities will occur during this stage.   Lire la suite »

janvier 042018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on January 3, 2018. You can see the presentation here:

Lire la suite »

décembre 182017

Chaplin Station - Temporary Driveway Realignment at 564 Eglinton Avenue West

WHAT WORK IS TAKING PLACE?

Beginning December 18, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and exiting the driveway.  A flag person will be on site to assist with traffic flow.

TIMING  Lire la suite »

décembre 052017

Chaplin Station Area - Planned Water Shut Off for Various Properties

CHAPLIN STATION - PLANNED WATER SHUT OFF
VARIOUS PROPERTIES - ONLY THOSE LISTED WILL BE AFFECTED

 MONDAY DECEMBER 11, 2017


WHAT WORK IS TAKING PLACE? Lire la suite »

novembre 032017

Sanitary Sewer Installation and Overnight Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Part of the work to be done within the north side work zone includes the installation of a new sanitary sewer system. The new sanitary sewer will run along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  

To complete the installation of the new sewer, crews will need to divert the existing sanitary sewer system flow. Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new pipes and property connections are installed. Lire la suite »

novembre 022017

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on November 1, 2017. You can see the presentation here:

Lire la suite »

octobre 242017

Traffic Change at Latimer & Eglinton for Chaplin Station Construction

What Work is Taking Place?

Since spring 2016, crews have been performing utilities relocation and support of excavation (shoring) in the vicinity of Chaplin Crescent and Eglinton Avenue West.  

As early as October 28, 2017, the work zone configuration will change in order to begin shoring and utility work (hydro, sewer) on the north side of Eglinton, while work continues on the south side of Eglinton.  Lire la suite »

octobre 132017

Chaplin and Avenue Stations Open House

Thank you for attending the open house about Chaplin and Avenue Stations on October 12, 2017. 

For those of you who missed it, the presentation is here: Lire la suite »

octobre 122017

Early Morning Equipment Move and Deliveries at Chaplin Station

What Work is Taking Place?

On Friday October 13, crews will move heavy equipment from the southwest work zone eastward along Eglinton Avenue to the southeast work zone.

On Tuesday October 17, crews will receive a large delivery of steel beams to be hoisted from Eglinton Avenue into the work zone.  Lire la suite »