Chaplin Crescent

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
novembre 262019

Construction Notice: Closure of Chaplin Crescent for Overnight Concrete Pour on Nov 28

*Updated on Nov 26 - This work has been rescheduled to Nov 28, due to inclement weather concerns* Lire la suite »

novembre 072019

Chaplin & Avenue Construction Liaison Committee Meeting - Nov 6, 2019

The construction liaison committee meeting of Chaplin & Avenue was held on November 6, 2019. You can view the presentation here:

octobre 302019

Central West Open House

Thank you for attending the Central West Open House on October 28, 2019. For those who weren't able to make it out in person, the presentation is here:

Lire la suite »

octobre 162019

Central Open House

Thank you for attending the Central Open House on October 15, 2019. For those of you who missed it, the presentation is here:

Download the presentation

octobre 072019

Update: Excavation at Chaplin Station

Excavation continues at the Chaplin Station.  Crews are excavating at the Main Entrance, located on the north side of Eglinton Avenue between Chaplin Crescent and Gilgorm Road, and at the Tertiary Entrance, located on the south side of Eglinton Avenue, east of Chaplin Crescent.Lire la suite »

Catégories:
septembre 252019

Tertiary Entrance Excavation Update at Chaplin Station

Information as of August 22, 2019

Excavation continues at the Chaplin Station Tertiary Entrance site, located on the south side of Eglinton Avenue, east of Chaplin Crescent, beside the former Toronto Fire Hall.  Excavators dig and remove soil from the work zone.  Excavated material will be transferred into dump trucks and hauled to an off-site facility.  Installation of tie-backs will take place from within the site as excavation progresses.  Excavation will begin at 6:00 a.m. on weekdays.

DETAILS Lire la suite »

Catégories:
septembre 132019

Temporary Traffic Change for Wet Utility Work at Chaplin Station September 16 – 24, 2019

On September 16, a temporary change will be implemented on Eglinton Avenue, east of Chaplin Crescent to accommodate wet utility work for Chaplin Station.  The northeast work zone will be extended further east and south of Latimer Avenue.  Traffic on Eglinton Ave will be shifted south.  No changes to pedestrian routes are anticipated.  Once the work is complete, the work zone will return to the current configuration.

Upcoming Traffic and Pedestrian Configuration Lire la suite »

juillet 312019

Pile Installation at Chaplin Station Secondary Entrance

In July and August 2019, crews will be installing micro piles at the Chaplin Station Secondary Entrance site, located on the southwest corner of Chaplin Crescent and Eglinton Avenue West.  Piles will form the future supports of the station entrance structure below ground.

Construction Configuration

Details Lire la suite »

juillet 242019

Main Entrance Excavation at Chaplin Station

What Work is Taking Place?

Beginning the week of July 29, 2019, crews will commence excavation at the Chaplin Station Main Entrance site, located on the north side of Eglinton Avenue, between Chaplin Crescent and Gilgorm Road.  Excavators will dig and remove soil from the work zone.  The excavated material will be transferred into dump trucks and hauled to an off-site facility.  Installation of tie-backs will take place from within the site as excavation progresses.

Current Construction Staging Lire la suite »