Chaplin Crescent

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
septembre 182020

Avenue & Chaplin CLC - Presentation Deck - September 9, 2020

Construction Liaison Committee of Avenue & Chaplin was held on September 9, 2020. You can see the presentation here.

Lire la suite »

juillet 172020

Update: Extended Construction Hours at Chaplin Station - July 2020

What Work is Taking Place?

Extended construction hours at Chaplin Station are underway and will continue in August 2020.  Activities take place at Main Entrance located on the north side of Eglinton Avenue West between Chaplin Crescent and Gilgorm Road, and at the Tertiary Entrance located on the south side of Eglinton Avenue, east of Chaplin Crescent.  Activities include, deep excavation, loading and hauling of excavated spoils, removal of struts and walers, and deliveries of structural materials. Lire la suite »

juillet 172020

Upcoming Concrete Pour at Chaplin Station - Saturday, July 18, 2020

What Work is Taking Place?

On Saturday July 18, 2020, a large concrete pour will take place at the Chaplin Station Main Entrance site.  900+ cubic metres of concrete will be poured into the station box underground to form an invert slab.  The invert slab will flatten the bottom of the tunnel so that track can eventually be laid.  Two concrete pumps will be placed within work zones and several concrete trucks will deliver concrete to the site every hour.  The pour will take approximately 14 hours to complete.

  Lire la suite »

juillet 162020

Notice of Extension: Closure of Chaplin Cres Road Closure for Traffic Bridge Removal Works June 8 – July 31, 2020

 What Work is Taking Place?

Please note that the closure of Chaplin Crescent between Eglinton Avenue and Russell Hill Road has been extended by two (2) weeks until July 31, 2020, while crews complete traffic bridge removal, utilities reinstatement, back-filling and paving at the intersection.  The Chaplin-Russell Hill laneway closure is also extended to July 31, 2020. Lire la suite »

juillet 142020

Trailer Installation at Chaplin Station Week of July 13, 2020

What Work Is Taking Place?

As early as the week of July 13, 2020, a new, double-stacked site trailer will be installed in the northwest corner of the Chaplin Station Main Entrance site (former Chaplin Parkette) located on the north side of Eglinton Avenue between Chaplin Crescent and Gilgorm Road.  Installation of the trailer is required to commence construction activities at the Secondary Entrance.  The trailer will remain in place into 2021.

Trailer Lire la suite »