Chaplin Crescent

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juillet 312019

Pile Installation at Chaplin Station Secondary Entrance

In July and August 2019, crews will be installing micro piles at the Chaplin Station Secondary Entrance site, located on the southwest corner of Chaplin Crescent and Eglinton Avenue West.  Piles will form the future supports of the station entrance structure below ground.

Construction Configuration

Details Lire la suite »

juillet 242019

Main Entrance Excavation at Chaplin Station

What Work is Taking Place?

Beginning the week of July 29, 2019, crews will commence excavation at the Chaplin Station Main Entrance site, located on the north side of Eglinton Avenue, between Chaplin Crescent and Gilgorm Road.  Excavators will dig and remove soil from the work zone.  The excavated material will be transferred into dump trucks and hauled to an off-site facility.  Installation of tie-backs will take place from within the site as excavation progresses.

Current Construction Staging Lire la suite »

juillet 242019

Temporary Lane Reduction at Chaplin Station Week of July 29, 2019

A temporary lane reduction will be in at Chaplin Station the week of July 29, 2019, while crews construct a pedestrian walkway and install a dewatering pipe.  Eglinton Avenue West will be reduced to one lane only between Gilgorm Road and Latimer Avenue, alternating traffic in each directi Lire la suite »

juillet 032019
juin 072019

Updated: Road Closures for Traffic Bridge Installation at Chaplin Station

 

Updated July 4, 2019

Update: Due to various unforseen circumstances the re-opening of Chaplin Cres will be on July 12th, 2019.


Lire la suite »

juin 042019

Weekend Road Closures at Chaplin Station - Extended June 7-10, 2019

Update: Weekend Road Closures at Chaplin Station - Extended

June 7 – 10, 2019

  Lire la suite »

mai 022019

Construction Notice: Overnight Hydro Utility Work at Chaplin Station

Overnight Hydro Utility Work at Chaplin Station

Week of May 5 – 10, 2019

Permit Number: 81015401

What Work is Taking Place? Lire la suite »

avril 252019

Construction Notice: Weekend Road Closures for Pile Installation at Chaplin Station May 2019

Weekend Road Closures for Pile Installation at Chaplin Station

May 2019

 (Update: May 2, 2019 - TTC#14 Glencarin Detour Map Added) Lire la suite »

avril 152019

Overnight Concrete Pour at Chaplin Station

Overnight Concrete Pour at Chaplin Station
Wednesday April 17, 2019


On Wednesday April 17, 2019, at 2:00 a.m., crews will perform a large concrete pour.  The concrete will form part of the roof of Chaplin Station.  To ensure the continuity and integrity of the activity, and to minimize the impact to TTC operations, the pour will be conducted overnight when traffic is lighter.  Some traffic restrictions will be in effect to accommodate equipment and truck access requirements.  Lire la suite »

avril 102019

Update: Resumption of Construction at Chaplin Station Tertiary Entrance

Update: Resumption of Construction at Chaplin Station Tertiary Entrance

In April 2019, crews will be resuming work at the Tertiary Entrance site, located east of Chaplin Crescent on the south side of Eglinton Avenue adjacent the old Toronto Fire Hall.  Pile installation of the north wall of the Tertiary Entrance (at Eglinton Avenue) will commence.  Pedestrians rerouting and truck staging will be in effect.  Please read ‘What to Expect’ below.

Upcoming Construction Configuration Lire la suite »