Chaplin Crescent

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juillet 052018

Chaplin - Avenue Construction Liaison Committee Meeting

The Avenue & Chaplin Construction Liaison Committee Meeting was held on July 4, 2018. You can see the presentation here:

Download the presentation

mai 232018
mai 032018

Chaplin - Avenue Construction Liaison Committee Meeting

The Avenue & Chaplin Construction Liaison Committee Meeting was held on May 2, 2018. You can see the presentation here:

Download the presentation

avril 092018

Chaplin & Avenue Construction Liaison Committee Meeting - April 4, 2018

The Avenue & Chaplin Construction Liaison Committee Meeting was held on April 4, 2018.

You can see the presentation here: Lire la suite »

mars 232018

Upcoming Traffic Change and Shoring Update at Chaplin Station

WHAT WORK IS TAKING PLACE?

Chaplin Station construction continues with a variety of ongoing construction activities. Traffic changes are required in order to continue to upgrade existing/install new utilities, continue shoring activities on the north side of Eglinton, and begin shallow excavation on the north side of Eglinton.

The new construction staging and associated traffic changes will be implemented as early as late March 2018. Lire la suite »

mars 222018

Central Open House (Chaplin Station to Leaside Station)

Thank you for attending the open house about Chaplin Station to Leaside Station on March 21, 2018.

For those of you who missed it, the presentation is here: Lire la suite »

mars 122018

Shoring at Chaplin Station Main Entrance

WHAT WORK IS TAKING PLACE?

Support of excavation (or shoring) continues at Chaplin Station. At the Main Entrance site, located on the northeast corner of Chaplin and Eglinton, there are some piles that remain to be installed.

As early as Wednesday, March 14, crews will begin piling activities at the Main Entrance. The drill will cross Eglinton to the Main Entrance site as early as Monday, March 12.

TIMING  Lire la suite »

mars 082018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on March 7, 2018. You can see the presentation here: Lire la suite »

février 282018

Special Pile Installation at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are currently completing support of excavation (or shoring) on the north side of Eglinton. As part of this work, two special polymer piles (vertical steel beams) will be installed.  Special polymer piles are large in depth and size.  Therefore, a longer drilling and concrete pouring period is required. To ensure the structural integrity of each pile, once installation begins, it cannot be stopped. Lire la suite »