Cross Passage Headwall Construction near Duncannon Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels required for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels.  Lire la suite »

juillet 212014

Work Zones to be shifted to the South Side of Eglinton at Chaplin

What is the purpose of the construction work at Chaplin?

Station headwalls create the frame for future underground stations, and are required to be in place prior to the arrival of tunnel boring machines at each of the station locations along the Eglinton Crosstown route. Construction of the headwalls requires a grout plant to be established nearby to pump a form of concrete, otherwise known as “grout”, to the station headwall location. Lire la suite »

juillet 172014

Work Zones to be shifted to the South Side of Eglinton at Chaplin

What is the purpose of the construction work at Chaplin?

Station headwalls create the frame for future underground stations, and are required to be in place prior to the arrival of tunnel boring machines at each of the station locations along the Eglinton Crosstown route. Construction of the headwalls requires a grout plant to be established nearby to pump a form of concrete, otherwise known as “grout”, to the station headwall location. Lire la suite »

juin 242014

Letter to residents addressing traffic concerns in the Chaplin and Eglinton area.

Dear Neighbour:

The Eglinton Crosstown is a light rail transit (LRT) line that will run across Eglinton Avenue between Mount Dennis (Weston Road) and Kennedy Station. This 19-kilometre corridor will include a 10-kilometre underground portion, between Keele Street and Laird Drive. It will provide a rapid and reliable service that will be up to 60% faster than bus service today, when it is completed in 2020. Lire la suite »