Cross Passage Headwall Construction near Duncannon Drive Continues - Stage 2

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
avril 27, 2015

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels required for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels. 

Why: Headwalls create the frame for future cross passages and/or stations, and are required to be in place prior to the arrival of tunnel boring machines along the Eglinton Crosstown route. Construction of the headwall requires a grout plant and grout lines to be established nearby to pump a form of concrete, otherwise known as “grout”, to the headwall location.  

Where: The work zone will extend from approximately Warren Road to Castle Knock Road on the south side of Eglinton Avenue West. The work zone will be separated from the right-of-way with traffic cones and concrete barriers and/or fencing.  Various traffic control measures will be in place on Eglinton Avenue near Duncannon Drive.  The construction zone will shift to the south side of Eglinton and will remain over the coming months for the construction of the headwall.

map headwall duncannon drive

When:  In April, there will be a new traffic pattern for the construction of the headwall for the cross passage at Duncannon Drive.  Construction is expected to continue to summer of 2015. Timelines may be rescheduled or adjusted due to weather conditions and unforeseen circumstances. 

Traffic Details

  • Traffic lanes on Eglinton Avenue will be reduced to one lane in each direction, while construction is set up on the south side of Eglinton Avenue West between Warren Road and Castle Knock Road.
  • Due to safety reasons, left turns from and onto Duncannon Drive will be prohibited. Right turns will be permitted. 
  • Due to safety reasons, left turns onto Tarlton Road will be prohibited. Right turns will be permitted.
  • On-street parking will not be permitted within the work zones.

Traffic delays are expected during construction. Please take care when travelling near construction areas. Pedestrian walkways will remain open. Please watch and obey traffic signs for the sake of everyone’s safety. 

Transit Information 

For the safety of transit riders, both eastbound and westbound TTC bus stops in the affected area will be relocated. Watch for posted signs and future information indicating the new locations.  

Noise and Vibration

Noise and vibration associated with construction can be expected with this work. 

Work Hours

Most of the work will be carried out between 7 a.m. and 11 p.m., 7 days a week. In certain situations, some late night and/or early morning works may be required to complete the work and keep construction moving.  The contractor will not always work during the extended hours, but may do so at its discretion. 

Please Contact Us

If you would like more detail about this work or any other aspect of the Eglinton Crosstown project, please do not hesitate to contact us.  We thank you for your continued patience as we work to build rapid transit.

Please support your local businesses during construction

Check out the website of The Eglinton Way BIA