Kennedy Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
décembre 132018

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Friday, December 14, 2018 from 4:00 a.m. until 10:00 a.m. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road. Lire la suite »

décembre 032018

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road as early as Friday, December 7, 2018 from 4:00 a.m. until 10:00 a.m. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road.

Lire la suite »

novembre 272018

Overnight Invert Concrete Pour at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, November 29, 2018 from 10:00 p.m. until completion. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road.   

Lire la suite »

novembre 222018

Eastern Works Open House (O’Connor Stop to Kennedy Station)

Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 082018

Hydro Pole and Duct Bank Installation Work at South Service Road at Kennedy Station

What Work is Taking Place?

In support of construction of the future Kennedy Station, crews will be conducting hydro pole and duct bank installation at the South Service Road. The work will begin as early as Friday, November 9th, and lasting for approximately two (2) weeks.

Lire la suite »

octobre 312018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:

Lire la suite »

octobre 192018

North Passenger Platform and Bus Loop Restoration at Kennedy Station

What Work is Taking Place?

Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Lire la suite »

octobre 122018

Update: Upcoming Traffic Changes at Kennedy and Eglinton Intersection in Support of Shoring Work

Originally Published: October 12, 2018

Updated: October 19, 2018

Updated: October 26, 2018

Updated: October 29, 2018

Updated: November 5, 2018 Lire la suite »

octobre 112018

Large Tower Crane Delivery and Installation at Kennedy Station

What Work is Taking Place?

On Tuesday, October 16, 2018 a large tower crane will be delivered to Kennedy Station in advance of deep excavation works. The tower crane will be erected at Compound 2, within the existing construction zone at Kennedy Station (adjacent to Transway Crescent). 

The tower crane will be erected on the concrete base (pictured below). Delivery and set-up will take one day to complete.   Lire la suite »

septembre 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:

Lire la suite »