Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Lire la suite »

octobre 112017

Overnight Work in the South Parking Lot at Kennedy Station

What Work is Taking Place?

As part of the ongoing work to construct Kennedy Station, crews will install temporary light poles and lines in the South Parking Lot starting as early as October 11, 2017. The work will be performed overnight in an effort to minimize disruption to the public and transit users.

Hours of Work Lire la suite »

septembre 282017

UPDATED: Ongoing Preparatory Works between Leslie and Midland: Street Furniture Removals

Updated: September 28, 2017
Original Issue Date: May 10, 2017

What Work is Taking Place? 

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Leslie Street and Midland Avenue. Lire la suite »

septembre 272017

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on September 26, 2017. You can see the presentation here: Lire la suite »

septembre 202017

Preliminary Notice to Businesses and Residents: Upcoming Power Outage Between Birchmount and Kennedy

What Work is Taking Place?

Since June 2017, crews have been upgrading and relocating existing hydro utilities in the area located just west of Birchmount Road to Kennedy Road in the vicinity of Eglinton Avenue East. To complete this work, a Hydro outage is required.

Hours of Work Lire la suite »

septembre 152017

Upcoming: North Entrance Closure and Demolition at Kennedy Station in Fall 2017

We have been busy building you the new 19-kilometre Eglinton Crosstown light rail transit (LRT) line!

This has involved lots of moving parts — excavations at future stations, relocating and upgrading utilities, road widening, and center-medians removal work for future stops.

Now we are working at the eastern end of the Crosstown LRT line at Kennedy Station — a future interchange station (pictured below). Lire la suite »

août 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Lire la suite »

août 292017

Parking Lot Reductions and Associated Works at Kennedy Station

What Work is Taking Place?

Parking will be displaced in the East and South Parking Lots at Kennedy Station to facilitate construction of the Kennedy Station. Works include: Lire la suite »

août 112017

Toronto Hydro-Electric System Limited (THESL) Relocation Work at Kennedy Station

What Work is Taking Place?
Crews will relocate and upgrade existing overhead hydro utilities between the West Service Roads to the East Service Roads of Eglinton Ave East in preparation for construction of the Kennedy Portal and the Kennedy LRT Station.