Overnight Temporary Left Turn Lane Restrictions at Warden Ave & Eglinton Ave E – February 14

What Work is Taking Place?

The eastbound and westbound left turn lanes at Warden Avenue and Eglinton Avenue East will be temporarily restricted on February 14, 2020 between the hours of 2:00 a.m. and 5:00 a.m. to support the construction of the future Golden Mile LRT Stop.

Work includes rail installation east and west of Warden Avenue, the left turn restrictions will allow crews greater access to the mid-block guideway work zone, and enough space to carry out the work safely.

Upcoming Traffic Configuration Lire la suite »

février 072020

Lane Restrictions at Warden Avenue and Eglinton Avenue East - February 11 – 21

Originally Posted: February 07, 2020

Updated: February 13, 2020

What Work is Taking Place

As part of the ongoing construction to support the future surface alignment for the Eglinton Crosstown LRT, lanes will be restricted at Warden Avenue to raise the existing maintenance holes to street level. Work will begin as early as Monday, February 11, 2020 and last through February 21, 2020. Lire la suite »

janvier 312020

TPSS 11 Utility Work at Warden Avenue and Eglinton Avenue East - February 3 – February 7, 2020

 

What Work is Taking Place

As part of the ongoing construction to support the future surface alignment for the Eglinton Crosstown LRT, lanes will be restricted at Warden Avenue to raise the existing maintenance holes to street level. Work will begin as early as Monday, February 3, 2020 and last for five (5) days.

Northbound and southbound lanes will be restricted on Warden Avenue at Eglinton Avenue East.

Work will include minor excavation, utility and grading work to raise the maintenance holes to ground level.

  Lire la suite »

janvier 292020

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on January 28, 2020. You can see the presentation here:

 

Download the presentation

novembre 272019

Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019

The construction liaison committee meeting of Pharmacy to Kennedy was held on November 26, 2019. You can see the presentation here:


Download the presentation

novembre 202019

Upcoming Crane and Building Delivery of TPSS 11 - Monday November 25 – Thursday November 28, 2019

 

What Work is Taking Place

The Traction Power Substation 11 (TPSS 11) building will be delivered to Scarborough Nissan on Monday November 25, 2019. The TPSS 11 will be delivered in three oversized loads. Vehicles carrying the loads will travel southbound on Warden Avenue and continue eastbound on Civic Road. 

Traffic will be temporarily stopped south of Civic Road in both directions to accommodate the delivery. Lire la suite »

novembre 202019

Upcoming Crane and Building Delivery of TPSS 11 - Monday November 25 – Thursday November 28, 2019

 

What Work is Taking Place

The Traction Power Substation 11 (TPSS 11) building will be delivered to Scarborough Nissan on Monday November 25, 2019. The TPSS 11 will be delivered in three oversized loads. Vehicles carrying the loads will travel southbound on Warden Avenue and continue eastbound on Civic Road. 

Traffic will be temporarily stopped south of Civic Road in both directions to accommodate the delivery. Lire la suite »

octobre 312019

UPDATED: EXTENSION OF OVERNIGHT WORK AT WARDEN AVENUE

Original Post: October 22, 2019

Updated: October 31, 2019

WHAT WORK IS TAKING PLACE?

 

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will work extended hours at the Traction Power Substation 11, located on the southeast side of Eglinton Avenue East and Warden Avenue. As early as Wednesday, October 23, 2019 work will take place between the hours of 7:00 p.m. to 5:00 a.m. Due to bad weather, overnight work at Warden will continue until Friday, November 8. Lire la suite »

octobre 252019

Eastern Works Open House

Thank you for attending the Easterm Works Open House on October 24, 2019. For those of you who missed it, the presentation is here:

 

 

septembre 252019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:

 