mars 132019

Updated: Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as March 16, 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.  Lire la suite »

mars 042019

Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the centre of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as mid-March 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.

Stage 2 Lire la suite »

février 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Lire la suite »

janvier 182019

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

Telecom work has been extended until the Spring 2019.

Lire la suite »

novembre 302018

Sidewalk Closures Required for Telecommunication Relocation Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting hydro pole and duct relocation work 50 meters south of Warden Avenue.

Starting as early as Monday, December 3rd, and lasting for approximately two (2) weeks, there will be intermittent sidewalk closure south west of Warden Avenue in order to safely carry out the work. Lire la suite »

novembre 222018

Eastern Works Open House (O’Connor Stop to Kennedy Station)

Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 142018

Boulevard Restoration Work Between Warden Avenue and Birchmount Road

Originally Published: November 14, 2018

Last Updated: November 29, 2018

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting boulevard restoration civil work including road widening along Eglinton Avenue East between Warden Avenue and Birchmount Road. Lire la suite »

novembre 062018

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

Crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road, as part of construction of the future surface section for the Eglinton Crosstown LRT.

Telecom work commenced in February and has been extended until the end of the year (Fall/Winter 2018).

Lire la suite »

novembre 052018

Hydro Work along Surface Section of the Eglinton Crosstown LRT at Warden Avenue

What Work is Taking Place?

In support of construction of the future At Grade stops, crews have been upgrading and relocating existing overhead hydro utilities between Pharmacy Avenue and Warden Avenue near Eglinton Avenue East.

Starting as early as Monday, November 5, 2018 and lasting for approximately two (2) weeks, crews will be conducting hydro pole installation at the north-west, north-east, and south-west corners of Warden Avenue and Eglinton Avenue East. Lire la suite »

octobre 312018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:

Lire la suite »