UPDATE: Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

Beginning May 19, 2018 work will get underway building the foundation and housing for the Facility Services Building for the TTC Line 1 Subway system. Crews will also undertake various activities inside the TTC station. Lire la suite »

mai 092018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on May 8, 2018. You can see the presentation here:

Download the presentation

mai 082018

Public Meeting of Facility Services Building at Eglinton Station

Thank you for attending the public meeting about Facility Services Building at Eglinton Station on May 7, 2018. You can see the presentation here:

Lire la suite »

mai 042018

Holly Street Closed at Eglinton for Toronto Hydro Work

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews have begun the next phase of re-routing existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.  

For this next stretch of the work, crews will be working to install new Toronto Hydro infrastructure within the City of Toronto’s public right-of-way. Crews may use a hydro-vacuum truck, excavators, jack-hammer and other construction equipment to complete the work. Lire la suite »

mai 032018

Short-term Closure of Eglinton Avenue for Toronto Hydro Work

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews have begun the next phase of re-routing existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.  

For this next stretch of the work, crews will be working to install new Toronto Hydro infrastructure within the City of Toronto’s public right-of-way across Eglinton Avenue East, east of Holly Street. Crews may use a hydro-vacuum truck, excavators, jack-hammer and other construction equipment to complete the work. Lire la suite »

mai 012018

RE-SCHEDULED: Overnight Work for Toronto Hydro Work at 90 Eglinton Avenue East

ORIGINAL POST: April 27, 2018

RE-ISSUE DATE: May 1, 2018

 

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews have begun the next phase of re-routing existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.   Lire la suite »

avril 202018

Upcoming Works at Eglinton Station: Next Phase of Support of Excavation

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring will be conducted in phases, beginning in the former TTC bus depot on the southeast corner of Yonge and Eglinton and along the south side of Eglinton Avenue between Duplex Avenue and Holly Street.  Lire la suite »

avril 112018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on April 10, 2018. You can see the presentation here:

Lire la suite »

avril 052018

Upcoming Works at Eglinton Station: Temporary Manhole Construction

What Work is Taking Place?

Construction of a temporary manhole at Eglinton Avenue West and Duplex Avenue is required to enable the continued relocation of utilities for the construction of Eglinton Station.

 

Hours of Work Lire la suite »

mars 222018

Scheduled Toronto Hydro Outage at 32 and 38 Berwick Avenue

What Work is Taking Place?

In order to prepare for construction of the new TTC emergency services building, crews will be installing new hydro infrastructure along Berwick Avenue between Duplex Avenue and Yonge Street. In order to complete the next phase of this work, crews will be installing new transformers at the corner of Duplex Avenue and Berwick Avenue. A hydro outage is required in order to safely carry out this work. The following properties will lose hydro service temporarily during this work: Lire la suite »