UPDATE: CROSS PASSAGE 10 AT LILLIAN STREET

Underground excavation work will commence in early August in the tunnels below Eglinton Avenue East at Lillian Street. This work will occur on a 24 hour basis with all works being completed below ground. The excavation will create a connection corridor underground between the north tunnel and the south tunnel. The work is expected to last for approximately two (2) weeks.   Lire la suite »

juillet 172019

Extension of Berwick Avenue Road Closure for TTC Line 1 Facility Service Building Construction - July 16 – 22, 2019

On July 5, 2019, Berwick Avenue closed between Duplex Avenue and Yonge Street to perform supporting construction activities for TTC’s Line 1 Subway Facility Services Building.  Followed by two weekend closures from July 19 – 22, 2019, and July 26 – 29, 2019.  An extension of the first closure, from July 15 – 19, 2019 is required due to longer than anticipated work times.


Road Closure Details Lire la suite »

juin 142019

Upcoming Berwick Avenue Road Closures for TTC Line 1 Facility Service Building Construction - July 2019

What Work is Taking Place?

In July 2019, crews will conduct a series of closures of Berwick Avenue between Duplex Avenue and Yonge Street to perform supporting construction activities for TTC’s Line 1 Subway Facility Services Building.  Due to the location of the new building, the work can only be carried out safely while the subway is not in operation.  Please see below the schedules of road closure and subway closure in July.

 

Road Closure Details Lire la suite »

mai 142019

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The presentation for the construciton liaison committee meeting of Eglinton and Mount Pleasant Stations for the month of May 2019 can be viewed here:

Download the presentation

avril 172019

Update: Cross Passage Dewatering System between Lillian Street and Redpath Avenue

WHAT WORK IS TAKING PLACE

The dewatering system at Cross Passage 10 site between Lillian Street and Redpath Avenue is now recommissioned and will operate on a 24 hour basis. Periodic maintenance will be required.

 

 

 

TRAFFIC, TTC AND PEDESTRIAN IMPACTS Lire la suite »

avril 032019

Upcoming Traffic Changes at Eglinton Station

What Work is Taking Place?

As decking nears completion at Eglinton Avenue and Holly Street, crews will be moving the work zone to the north side of Eglinton Avenue between Holly Street and Dunfield Avenue. The next phase (depicted below) will take approximately 2-3 months to complete. 

 

Hours of Work Lire la suite »

mars 202019

Central East Open House (Eglinton to Laird Stations)

Thank you for attending the Central East Open House on March 19, 2019. For those of you who missed it, the presentation is here:

Download the presentation

mars 192019

Central West Open House (Fairbank to Eglinton Stations)

Thank you for attending the Central West Open House on March 18, 2019. For those of you who missed it, the presentation is here:

 

Download the presentation

mars 132019

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on March 12, 2019. You can see the presentation here: 

 

Download the presentation

mars 132019

Emergency Roadway Repairs on Yonge Street at Eglinton Station

What Work is Taking Place?

In order to carry out repairs on the asphalt on Yonge Street, crews have shifted traffic on Yonge Street to the west side, closed the north-south crosswalk on the east side of the Yonge-Eglinton intersection, and re-opened the crosswalk on the west. This will be temporary until the repairs are complete on March 16.

On completion, the traffic will revert back to the previous stage to complete the excavation around the TTC Line 1 Subway box.

 