Yonge Street

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juillet 122017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on July 11, 2017. You can see the presentation here:

Lire la suite »

juin 212017

Upcoming Sanitary Sewer Connection at Eglinton Station

What Work is Taking Place

To prepare for the construction of Eglinton Station, crews have been relocating existing water mains and sanitary sewers in the vicinity of Eglinton Avenue and Yonge Street.  To complete this work, crews need to connect the new sanitary sewer with the existing sewer located at the northwest corner of the Yonge-Eglinton intersection.  Lire la suite »

juin 142017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on June 13, 2017. You can see the presentation here:

Lire la suite »

juin 092017

Dewatering System Installation Eglinton Avenue East from Lillian Street to Redpath Avenue

What Work is Taking Place

The term “dewatering” means pumping from the ground water at a site where there will be excavation.  At Eglinton Avenue East between Lillian Street and Redpath Avenue, half a dozen small wells will be drilled for the future Cross Passage. The volume of soil that requires dewatering is significant.  The wells will be drilled and shallow trenches will be required to lay the pipes, pumps, wells and valves to do the work.   Lire la suite »

mai 022017

Upcoming Works at Eglinton Station: Utilities Relocations – Stage 3

What Work is Taking Place

Work to replace and relocate existing utilities continues to make way for the future Eglinton interchange station. Storm and sanitary sewers, water mains, hydro ducts, and telecommunications utilities are being replaced and relocated in a series of stages. During this third stage, work will take place on the south side of Eglinton Avenue, east and west of Yonge Street. Lire la suite »

avril 202017

UPDATE: Demolishing the Abandoned TTC Bus Depot

What Work is Happening?

  • The abandoned TTC Bus Depot (pictured below) is being demolished to make way for the new Eglinton LRT Station’s primary entrance (pictured at bottom) and new developments at Yonge and Eglinton.

Progress to Date

  Lire la suite »