Shoring and Guide Wall Construction at Fairbank Station Main Entrance

 
novembre 29, 2016

What Work is Taking Place? 

Beginning in late November 2016, crews will start support of excavation work, also known as shoring, at the future Fairbank Station.  The main entrance is located on the southeast corner of Eglinton Avenue West and Dufferin Street. 

Shoring is a common step in the process of constructing the foundation of a building.  Steel piles, as well as braces and tie-backs, will be installed around the perimeter of the station entrance to support excavation. Prior to installation of the piles, crew will construct a concrete guide wall on either side of the secant wall to ensure the alignment and verticality of the piles. 

This stage will take approximately seventeen (17) weeks to complete.

Hours of Work

  • This work will be conducted Monday through Friday between the hours of 7:00 AM and 11:00 PM, with crews working until 11:00 PM on a regular basis
  • The contractor may not always work during the permitted hours, but may do so at its discretion
  • In the event that overnight work is required, Metrolinx and CTS will notify the public in advance and monitor activities throughout
  • Work is subject to permits and all relevant approvals, and may be rescheduled due to weather or unforeseen circumstances

Fairbank Shoring

What to Expect

  • Noise in the area caused by a pile drill, crane, loaders, trucks and other construction equipment
  • Dust from drilling activity and debris removal 
  • Truck traffic entering and exiting the work zone 
  • In addition to construction activity, equipment and material storage within designated work zones
  • For safety purposes, metal fencing has been erected around the work zone

Pedestrian Details

  • While pedestrian access will be maintained, temporary sidewalk closures or pedestrian rerouting may be in effect due to ongoing utilities relocation work at the intersection

Traffic Details

  • Temporary lane reductions may be in effect due to ongoing utilities relocation work at the intersection
  • Truck traffic will enter and exit site from the north and southwest sides of the work zone
  • Motorists may experience delays while trucks enter and exit the work zone
  • A flag person will be present to direct truck and pedestrian traffic
  • As always, please take care when travelling near construction zones

TTC Details

Three (3) TTC bus stops at the intersection of Eglinton Avenue West and Dufferin Street have been relocated to accommodate various stages of station construction:

  • The TTC bus stop on the southwest corner has been relocated approximately 70 meters to the west 
  • The TTC bus stop on the northwest corner will be relocated approximately 75 meters to the north  
  • The TTC bus stop on the northeast corner will be relocated approximately 170 meters to the west

Please look for signage informing passengers of the new temporary stops.

Contact Us

For more information about this work, please contact Stas Ukhanov at 416-782-8118 or

crosstown@metrolinx.com.

 

Thank you for your patience as we work to build this important project

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.