What's New?

 
Syndicate content
 
January 18 2018

Tunnel Connection Boreholes and Concrete Backfilling for the Main Entrance at Avenue Station

WHAT WORK IS TAKING PLACE?

To prepare for upcoming mining works at Avenue Station, crews need to fill portions of the completed tunnels with concrete. There are two separate phases to this work. Work will begin as soon as January 22, 2018.

PHASE 1 - DRILLING BORE HOLES Read more »

January 18 2018

Temporary Driveway Alignment Change at 564 Eglinton Avenue West for Chaplin Station

WHAT WORK IS TAKING PLACE?

Beginning January 22, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and existing the driveway.  A flag person will be on site to assist with entry and egress.

TIMING  Read more »

January 17 2018

Overnight Sewer Replacement at Oakwood Station

Crews will replace a sewer line at the intersection of Oakwood Avenue and Eglinton Avenue. A portion of the work will take place within the existing construction site. The work outside of the existing construction zone will be completed overnight to minimize disruption to traffic, pedestrians and TTC services. Work will be completed in three (3) stages to further minimize disruption. Read more »

January 16 2018

Rescheduled: Overnight Sanitary Sewer Relocation at Brentcliffe Portal January 16th to 21st from 9:00 p.m. to 5:00 a.m.

Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018 and Januaey 16, 2018

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place? Read more »

January 15 2018

Equipment Move at Caledonia Station

What Work is Taking Place?

On Monday January 15 and Tuesday January 16, 2018, crews will be moving equipment at the Caledonia Station site.  To facilitate this equipment move, temporary closure of the westbound curb side lane as well as the north sidewalk at Eglinton Avenue West and Blackthron Avenue is required. Read more »

January 15 2018

Updated: Ventilation Fan Works at Laird Station

Original Issue Date: December 18, 2017

What Work is Taking Place?

Starting as soon as mid-January 2018, crews will complete electrical connections for ventilation fans within the existing tunnels underneath Eglinton Avenue. Read more »

January 12 2018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on January 11, 2018. You can see the presentation here:

Read more »

January 12 2018

Overnight Monitoring Installations Around the TTC Eglinton West Station Bus Loop

WHAT WORK IS TAKING PLACE?

Geotechnical monitoring instruments are installed in the vicinity of the station construction to monitor the ground conditions as construction is underway. 

Monitoring instruments are regularly checked to measure any movements of the ground and assess if there is a need for additional measures. 

The majority of the monitors for Cedarvale Station were installed in late 2016/early 2017. Read more »

January 11 2018

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on January 10, 2018. You can see the presentation here:

Read more »