Allen Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
October 232017

Eglinton Lane Reduction for Cedarvale Station Utility Work

What Work is Taking Place?

  • To accommodate the continued utility works for Cedarvale Station, crews will reduce eastbound Eglinton Avenue from Park Hill Road to Allen Road to one lane to access two maintenance manholes.

Timing

  • The lane reduction is scheduled for October 23 – 27 from 10:00 AM to 3:00 PM daily to reduce impact on peak traffic hours.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

What to Expect

  • Eglinton Avenue will be reduce
October 182017

Preparing to Realign Allen Road South

PREPARING TO REALIGN ALLEN ROAD SOUTH

In early 2018, the construction work zones and traffic set up will change again for the next phase of support of excavation (shoring) activities on the north side of Eglinton Avenue West at Allen Road.

This requires the Allen Road South off-ramp to be realigned approximately 20m west.

The existing All Road South off-ramp will be in place as-is until early 2018.


What Work is Taking Place? Read more »

October 062017

Overnight and Early Morning Works at Cedarvale Station for Roof Slab Concrete Pour and Traffic Deck Coating

What Work is Taking Place?

 

  • Next week, two nights of overnight work are required and one early morning concrete pour is planned.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Traffic Deck Coating

TUESDAY OCTOBER 10 at 7PM – WEDNESDAY OCTOBER 11 at 5AM

WEDNESDAY OCTOBER 11 at 7PM – THURSDAY OCTOBER 12 at 5AM

  Read more »

September 292017

Cedarvale Station: Overnight Crosswalk Line Painting & Road Decking Inspection - Oct 1 & Oct 2

What Work is Taking Place?

  • Two nights of overnight work on Eglinton Avenue West at Allen Road are required.
  • Work will be done overnight while traffic volumes are low.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Crosswalk Line Painting

MIDNIGHT on SUNDAY, OCTOBER 1 until APPROXIMATELY 2AM on MONDAY, OCTOBER 2 Read more »

September 282017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on September  27, 2017. You can see the presentation here: Read more »

September 222017
August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »

August 252017

Cedarvale Station: Road Closures for Utility Relocation & Support of Excavation

Updated: August 25, 2017
Original Issue Date: June 28, 2017

What Work is Taking Place?

The Cedarvale Station work zones are now in full swing as crews complete tunnel concrete pours, utility relocation, and support of excavation activities.

To continue to relocate and upgrade storm and sanitary sewer infrastructure and complete support of excavation, traffic changes in the vicinity of Cedarvale Station are required.

Throughout the Summer 2017, the following roads were closed at Eglinton Avenue West: Read more »

July 272017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on July 26, 2017. You can see the presentation here:

Read more »