June 222017

Storm Sewer Connection in Cedarvale Park

What Work is Taking Place?

In preparation for the construction of Cedarvale Station, several storm and sanitary sewers must be reconfigured prior to the commencement of the support of excavation works. As part of one of these relocations, an existing connection must be enabled in one of the storm sewers at Cedarvale Park.

Crews will occupy a small portion of the park in the vicinity of an existing manhole (see picture below) in order to conduct the works.

Timing Read more »

June 092017

UPDATE: Cedarvale Station Support of Excavation

Original issue date: March 14, 2017
Re-issue date: June 9, 2017

UPDATE: Cedarvale Station Support of Excavation

By the end of 2015, tunneling works in the vicinity of Allen Road had concluded. Throughout 2016 and the beginning of 2017, crews conducted preparatory works for the future Cedarvale Station construction. Read more »

June 012017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on May 31, 2017. You can see the presentation here:

Read more »

April 242017

Upcoming Works at Cedarvale Station: Utilities Relocations

 

Upcoming Works at Cedarvale Station: Utilities Relocations 

  Read more »

April 132017

Upcoming Works at Cedarvale Station: Tunnel Invert Concrete Pour

Upcoming Works at Cedarvale Station: Tunnel Invert Concrete Pour 

  Read more »

March 312017

LOW WATER PRESSURE NOTICE: Watermain Investigation Work

What Work is Taking Place?

On April 3, 2017, crews will begin subsurface utility engineering (SUE) investigation of a large 900mm watermain in the Eglinton Avenue West and Chaplin Crescent area.  The watermain will be exposed to determine the utility and ground conditions in advance of wet utilities relocation.  Most of the work will take place within the existing traffic staging at Chaplin Crescent and Eglinton Avenue West. Read more »

March 292017

Cedarvale Station Open House

Thank you for attending our Cedarvale Station Open House on March 28, 2017.

For those of you who missed it, the presentation is here:

Read more »

March 222017

Support of Excavation at Cedarvale Station

What Work is Taking Place?

  • Over the last year tunnel work in the vicinity of Allen Road has concluded and preparatory work for station construction has started. The next phase of work will involve further utility relocations as well as the start of support of excavation work (also known as shoring) for the future Cedarvale Station.
  • The entire shoring and road decking installation process will take approximately 18-24 months to complete and will be conducted in phases.
March 202017

Tunnel Invert Concrete Pour at Allen Rd and Eglinton

What Work is Taking Place?

  • To prepare for track and system installation in the new LRT tunnels, concrete must be poured to form the foundation of the track.