June 092017

UPDATE: Cedarvale Station Support of Excavation

Original issue date: March 14, 2017
Re-issue date: June 9, 2017

UPDATE: Cedarvale Station Support of Excavation

By the end of 2015, tunneling works in the vicinity of Allen Road had concluded. Throughout 2016 and the beginning of 2017, crews conducted preparatory works for the future Cedarvale Station construction. Read more »

June 012017

Cedarvale - Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on May 31, 2017. You can see the presentation here:

Read more »

April 242017

Cedarvale Station Utilities Relocations

Original Issue Date: April 24, 2017
Updated: August 10, 2017 

What work is taking place?

To make way for the future Cedarvale interchange station, work will commence to replace and relocate existing utilities in the area of Allen Road and Eglinton Avenue West. Work is permit pending. Read more »

April 132017

Upcoming Works at Cedarvale Station: Tunnel Invert Concrete Pour

Upcoming Works at Cedarvale Station: Tunnel Invert Concrete Pour 

  Read more »

March 312017

LOW WATER PRESSURE NOTICE: Watermain Investigation Work

What Work is Taking Place?

On April 3, 2017, crews will begin subsurface utility engineering (SUE) investigation of a large 900mm watermain in the Eglinton Avenue West and Chaplin Crescent area.  The watermain will be exposed to determine the utility and ground conditions in advance of wet utilities relocation.  Most of the work will take place within the existing traffic staging at Chaplin Crescent and Eglinton Avenue West. Read more »

March 292017

Cedarvale Station Open House

Thank you for attending our Cedarvale Station Open House on March 28, 2017.

For those of you who missed it, the presentation is here:

Read more »

March 222017

Support of Excavation at Cedarvale Station

What Work is Taking Place?

  • Over the last year tunnel work in the vicinity of Allen Road has concluded and preparatory work for station construction has started. The next phase of work will involve further utility relocations as well as the start of support of excavation work (also known as shoring) for the future Cedarvale Station.
  • The entire shoring and road decking installation process will take approximately 18-24 months to complete and will be conducted in phases.
March 202017

Tunnel Invert Concrete Pour at Allen Rd and Eglinton

What Work is Taking Place?

  • To prepare for track and system installation in the new LRT tunnels, concrete must be poured to form the foundation of the track.
October 112016

Geotechnical Instrumentation and Monitoring at Cedarvale Station

What Work is Taking Place?

  • Geotechnical instrumentation and monitoring is required for the protection of the existing buildings and underground utilities by monitoring movements of the ground, support of excavation, utilities, structures and groundwater regime, prior, during and following construction in order to assess the need for implementation of mitigation measures.
  • Crews will drill approximately 15+ boreholes in the Cedarvale Station area to install geotechnical instrumentation and monitoring equipment. 

Timing