Associated Works at Eglinton Station

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
February 10, 2018

What Work is Taking Place?

As part of the ongoing works at 90 Eglinton Avenue East, crews will be delivering concrete at the site beginning as early as Monday, February 12 to Sunday, April 15, 2018. To facilitate this delivery, concrete trucks will be arriving to site from the east along Eglinton Avenue East, turn down Dunfield Avenue and reverse into the construction site.  

Hours of Work

  • Work is expected to occur from as early as Monday, February 12 to Sunday, April 15, 2018 from 7:00 a.m. to 5:00 p.m. 
  • Weekend work may be planned at a later date.
  • Work may be rescheduled due to weather conditions of unforeseen circumstances.

What to Expect

  • Traffic control/flagman will be around the Dunfield Avenue and Eglinton Avenue East intersection and will hold traffic until the truck has entered into the construction site.
  • Expect traffic delay in this area.

Traffic and Pedestrian Impacts

  • Traffic control/flagman may stop traffic intermittently for trucks to safely enter and exit the site for deliveries.
  • Traffic control/flagman will be on the west side of Eglinton Avenue East and Dunfield Avenue around the intersection to ensure pedestrians do not step off sidewalk until the hazards has been cleared.
  • All sidewalks will be maintained during this work.

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

 

For more information, please contact Phil Rodriques at the East Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.