April 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »

March 072016
February 242016

Demolition Work at Future Avenue Station

Upcoming Work – Demolition and Selective Street Furniture Removal Read more »

February 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Read more »

January 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Read more »

December 182015

Tunnelling: What You May Experience

Dear Neighbour:

As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »

December 182015

Tunnelling: What You May Experience

Dear Neighbour:

As you may know, the Eglinton Crosstown is a 19-kilometre light rail transit that includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunneled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel about 10 metres per day. TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area. Read more »

November 182015

Monitoring Equipment Installation along Eglinton Avenue West at Spadina Road

What: Monitoring equipment will continue to be installed at major intersections along Eglinton Avenue West. This equipment will measure important data related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue West if needed.   Read more »

November 182015

Monitoring Equipment Installation along Eglinton Avenue West at Spadina Road

What: Monitoring equipment will continue to be installed at major intersections along Eglinton Avenue West. This equipment will measure important data related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue West if needed.   Read more »