Bathurst Street

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
September 032014

Open houses in September

Metrolinx is hosting three open houses in September at various locations along the Eglinton corridor to provide an update on current Crosstown construction.

Join us at one of the following sessions to hear what is happening, why it needs to happen and how it may impact you:

Tuesday, September 9, 2014

7:00 - 9:00 pm Read more »

August 282014

Long-term Closure of Peveril Hill North at Eglinton Avenue West

What we are building

What:  Construction of the headwalls for the future Bathurst station requires a small grout plant to be established nearby to pump a form of concrete, otherwise known as “grout”, to the station headwall location. In order to minimize road occupancy on Eglinton Avenue West this grout plant will be located within a section on Peveril Hill North, south of Eglinton. Some road adjustments will take place to accommodate the grout plant. Read more »

August 252014

Cross Passage Headwall Construction for Twin Tunnels Stage 2 – Southside Switch

What we are building

What:  A cross passage is a smaller tunnel placed between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the cross-passage required for future maintenance of the tunnels. Headwalls are underground support walls. Read more »

August 052014

Short Term Lane Closures along Eglinton Avenue West for Monitoring Equipment Installation Black Creek Drive -Yonge Street Summer 2014 - Summer 2015

What work is starting?

What: Crews will be installing ground movement monitoring equipment.
 
Why: Monitoring equipment will provide information on the ground conditions during excavation and tunnelling activities to the construction team. Read more »

July 182014

Update: Cross Passage Headwall Construction near Vesta Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels. Read more »