Bayview Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
August 292016

Bell Utility Relocations at Leaside Station

What work is taking place? 

  • To prepare for future construction of Leaside Station, crews will complete substantial utility relocations around the intersection at Eglinton Avenue East and Bayview Avenue.
  • The first stage of utility relocations includes relocation of existing underground Bell utilities.

Timing Read more »

August 112016

UPDATED: TTC DETOUR NOTICE - Eglinton Closure and Detour for Road Deck Repair: NEW DATE: Saturday, August 27 from 4 a.m. to 10 p.m.

Update

NEW DATE: Saturday, August 27 from 4:00 AM to 10:00 PM

ALTERNATIVE DATE: Saturday, September 10 from 4:00 AM to 10:00 PM

Transit Information

Relocation and re-routing of bus stops is done in consultation between TTC and Metrolinx to ensure construction can continue safely while minimizing the impact on the community and customers. Read more »

August 112016

Eglinton Closure and Detour for Road Deck Repair: Saturday, August 27 from 4 a.m. to 10 p.m.

What Work is Taking Place? 

As construction continues on the emergency exit building near Leaside High School, Eglinton Avenue East is required to be temporarily closed between Donlea Drive and Hanna Road, in order to remove and replace existing road decking.

Timing Read more »

July 132016

Subsurface Utility Engineering (SUE) Investigations at Bayview and Eglinton

What Work is Taking Place?

  • To prepare for future construction of the Leaside Station, crews will be conducting Subsurface Utility Engineering investigations along Eglinton Avenue East to determine the location and depth of existing utilities.
  • Crews will drill and use a vacuum truck overtop of existing utilities within the boulevard and roadway, then a surveyor will examine the utilities to obtain coordinates for design purposes.

Timing Read more »

July 132016

Median Removals and Temporary Traffic Light Installation at Leaside Station

What Work is Taking Place?

To prepare for future construction of the Leaside Station, crews will remove existing medians on Bayview Avenue, north and south of Eglinton Avenue. Crews will also be installing temporary traffic lights around the intersection at Eglinton Avenue East and Bayview Avenue. 

Timing Read more »

July 112016

Cross Passage Construction: Eglinton Avenue East at Walder Avenue

What

A cross passage is a small passageway built to connect the eastbound and westbound tunnels for maintenance and emergency purposes. Dewatering equipment is used at street level on Eglinton Avenue above the cross passage location. Dewatering is the process of removing groundwater from around the tunnel level below. The dewatering equipment will be in place for the duration of the building of the cross passage. Read more »

June 232016

Leaside Station Open House

Thank you for attending our Leaside station open house on June 22, 2016. 

For those of you who missed it, the presentation is here:

June 232016

Tunnelling: What You May Experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »

June 132016

Restoration work at Eglinton Avenue East and Bayview Avenue

What work is starting?

What: Bayview Station headwall work is complete. Crews will begin the following restoration work:

  • Restoring the sidewalk on the south side of Eglinton Avenue East, east of Bayview Avenue.
  • Restoring hydro poles and overhead wires to their original locations, on the south side of Eglinton Avenue East, west of Bayview Avenue.

Why:    Read more »

June 132016

Overnight Construction at Bayview and Eglinton Intersection

What work is starting?

What: Removal of the jet-grout delivery trench and road surface restoration within the intersection of Bayview Avenue and Eglinton Avenue East.

When: Wednesday, June 15, 2016 at 9:00 p.m. to Thursday, June 16, 2016 at 5:00 a.m.

Where: Crews will be working within the intersection at Bayview Avenue and Eglinton Avenue East.   Read more »