Brentcliffe Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
October 162017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 5:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »

October 062017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on October 5, 2017. You can see the presentation here:

Read more »

October 052017

Tunnel Backfilling Brentcliffe Road to Laird Drive

What Work is Taking Place?

To support the ongoing mining works at the future Laird Station, a layer of backfill (granular material) will be added to the base of the existing tunnel from the Brentcliffe Portal to Laird Drive. 

Backfill material will be stockpiled and then be pushed in to the tunnel at Brentcliffe Portal and inside the tunnels towards Laird Drive. Compaction of the material will occur inside of the tunnels. Read more »

October 042017

Geotechnical Equipment Installations and Monitoring on Thursfield Crescent for the Brentcliffe Portal and Surface Stops

What Work is Taking Place?

As part of the ongoing construction works for the future Brentcliffe Portal and Surface Stops, above ground and in-ground monitoring points will be installed on the City Right-of-Way, which may include the roadway, sidewalks and/or driveways on Thursfield Crescent.

Once installed, the instruments will remain at these locations for the length of the project. Monitoring allows crews to evaluate the impact of construction works. Read more »

September 132017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area.   Read more »

September 082017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on September 7, 2017. You can see the presentation here:

Read more »

August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »

August 012017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 3:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area.   Read more »

July 142017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on July 13, 2017. You can see the presentation here:

Read more »