October 112019

Concrete Pours at Caledonia Station - October 2019

What Work is Taking Place?

In October 2019, crews will at Caledonia will perform several large concrete pours. Westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way.

Hours of Work  Read more »

June 142019

CONCRETE POUR AT CALEDONIA STATION JUNE 15, 2019

What Work is Taking Place?

On Friday, June 15th 2019, crews at Caledonia will perform a concrete pour. Eglinton Ave W will remain reduced to one (1) lane travelling westbound from Blackthorne Ave to the entry of the Westside Mall. 

Hours of Work  Read more »

June 132019

Update: RAIL DELIVERY & LANE REDUCTION AT CALEDONIA STATION

What Work is Taking Place?

On Monday, June 17th 2019, crews at Caledonia Station will begin unloading and storing the rails for installation in the tunnels. Eglinton Avenue West will be reduced to one (1) lane travelling westbound from Blackthorne Ave to the entry of the Westside Mall for approximately three (3) weeks.

 

Hours of Work  Read more »

May 062019

HYDRANT FLOW TEST AT CALEDONIA STATION MAY 8, 2019

What Work is Taking Place?

On Wednesday, May 8th 2019 at 9:00am, City of Toronto and CTS crews will be performing a hydrant water flow test at the Caledonia site. Construction staging will remain the same.

 

Hours of Work Read more »