Chaplin Station - Temporary Driveway Realignment at 564 Eglinton Avenue West

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
December 18, 2017

WHAT WORK IS TAKING PLACE?

Beginning December 18, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and exiting the driveway.  A flag person will be on site to assist with traffic flow.

TIMING 

  • December 18 – 22, 2017
  • Delays can be expected during construction hours, 7:00AM – 11:00PM 

WHAT TO EXPECT

  • Drivers can expect delays when entering and exiting the driveway of 564 Eglinton Avenue West