March 022018

Sidewalk Repairs at Leaside Station

WHAT WORK IS TAKING PLACE?

On Monday, March 5th Leaside station crews will complete repairs on a section of sidewalk on the north side of Eglinton Avenue between Bayview Avenue and the Metro driveway. 

 Read more »

March 022018

OVERNIGHT WORK TO PREPARE FOR WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

ORIGINAL POST: FEBRUARY, 16, 2018

RE-ISSUE DATE: MARCH 2, 2018

WATERMAIN LINING OVERVIEW Read more »

March 012018
February 282018

Special Pile Installation at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are currently completing support of excavation (or shoring) on the north side of Eglinton. As part of this work, two special polymer piles (vertical steel beams) will be installed.  Special polymer piles are large in depth and size.  Therefore, a longer drilling and concrete pouring period is required. To ensure the structural integrity of each pile, once installation begins, it cannot be stopped. Read more »

February 272018

Overnight Piling Work February 28 for Science Centre Station

What Work is Taking Place?

Crews will be drilling piles within the Don Mills Road and Eglinton Avenue East intersection as part of the Support of Excavation work at the future Science Centre Station. 

Due to the location of the piles and in an effort to minimize disruption to local traffic and commuters work will be performed overnight on Wednesday, February 28, 2018 from 8:00 p.m. to 5:00 a.m. Thursday morning. The intersection will be restored in advance of morning rush hour. Read more »

February 272018

UPDATE: Overnight Work for GO Transit Improvements at Kennedy and Partial Closure of Southern Section of East Platform

Originally Published: February 8, 2018

Updated: February 12, 2018, February 16, 2018 and February 27, 2018

What Work is Taking Place?

Kennedy Station and its environs are changing every day.

As part of GO Transit Improvements at Kennedy, crews will close a southern portion of the existing east platform on the Stouffville Line as early as Monday, February 19, 2018 to facilitate shoring for the GO underpass, the construction of a new pedestrian underpass, and the shoring for the Eglinton Crosstown LRT Box under the GO corridor. Read more »

February 262018

Upcoming Works at Eglinton Station: Next Phase of Support of Excavation

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring will be conducted in phases, beginning in the former TTC bus depot on the southeast corner of Yonge and Eglinton and along the south side of Eglinton Avenue between Duplex Avenue and Holly Street.  Read more »

February 262018

Sewer Lining Activities at Oakwood Station-Updated

What Work is Happening?

Crews must install sewer linings to the existing sewer infrastructure on Eglinton Avenue West between Oakwood Avenue and Times Road. Read more »

February 232018

Mining Equipment Mobilization - 24 Hour Work - Avenue Station Main Entrance

WHAT WORK IS TAKING PLACE?

Mining operations will begin at the Avenue Station Main Entrance in Spring 2018. The mining equipment is planned to be delivered to the site during the weekend of March 2 – 4. 