September 282017

Tunnel Concrete Pour for Avenue Station

What Work is Happening? 

To prepare for upcoming mining works at Avenue Station, crews need to fill portions of the completed tunnels with concrete. 

Hours of Work Read more »

September 252017
September 222017
September 202017

Preliminary Notice to Businesses and Residents: Upcoming Power Outage Between Birchmount and Kennedy

What Work is Taking Place?

Since June 2017, crews have been upgrading and relocating existing hydro utilities in the area located just west of Birchmount Road to Kennedy Road in the vicinity of Eglinton Avenue East. To complete this work, a Hydro outage is required.

Hours of Work Read more »

September 192017

Mining at Laird Station Main Entrance

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Laird Station, are going to be “mined.” 

Excavation of the main entrance at Laird Station is complete and mining will begin soon. Read more »

September 192017
September 182017

Site Service Connections at Oakwood Station

What work is taking Place?

Crews will complete temporary water and sanitary connections at the Main and Secondary Entrance. Read more »

September 152017

Overnight Stormwater Relocation Work Week of September 17 for Science Centre Station

What Work is Taking Place? 

 Crews will relocate an existing stormwater on Eglinton Avenue East just east of Don Mills Road to support the upgrade of existing water infrastructure at the future Science Centre Station.

Timing Read more »