Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
May 082019

Extended Work Hours Leaside Station

WHAT WORK IS TAKING PLACE?

Beginning as early as May 13, 2019, crews will work extended hours at Leaside Station. Work will be carried out between 5:00 a.m. and 11:00 p.m., Monday through Saturday. Site-based noise mitigation measures have been implemented to reduce disruption due to noise. Read more »

May 072019

Black Creek Closures and Overnight Work for West Portal & Elevated Guideway Cantilever Removal & Patchwork

As part of the ongoing works on the West Portal & Elevated Guideway, over a two night period crews will be removing cantilevers across Black Creek Drive on May 10 to 12, 2019. Black Creek Drive southbound and northbound will be closed one at a time as follows to safely carry out the work: Read more »

May 062019

Eglinton Avenue Overnight Work and Weekend Closure between Park Hill Road and Allen Road South

What Work is Taking Place?

To accommodate re-bracing and replacement of decking between Park Hill Road and Allen Road South, Eglinton Avenue will close for a weekend to carry out the works. Paid-duty officers and/or flag persons will be on site to assist in directing traffic.

Hours of Work Read more »

May 062019

HYDRANT FLOW TEST AT CALEDONIA STATION MAY 8, 2019

What Work is Taking Place?

On Wednesday, May 8th 2019 at 9:00am, City of Toronto and CTS crews will be performing a hydrant water flow test at the Caledonia site. Construction staging will remain the same.

 

Hours of Work Read more »

May 022019

Construction Notice: Overnight Hydro Utility Work at Chaplin Station

Overnight Hydro Utility Work at Chaplin Station

Week of May 5 – 10, 2019

Permit Number: 81015401

What Work is Taking Place? Read more »

May 022019

Upcoming Traffic Configuration Change at Fairbank Station

What Work is Taking Place?

As early as May 6, 2019, the traffic configuration at Dufferin Street and Eglinton Avenue will change to accommodate the next stage of construction.  Traffic on Eglinton Avenue will be shifted south and construction will return to the north side of Eglinton Avenue between Shortt Street and Dufferin Street.  The work zone on the north side of Eglinton Avenue, east of Dufferin Street will remain in place.

Hours of Work  Read more »

May 012019

Construction Notice: Lane Reductions to facilitate hydro utility relocation at the East Service Road

Lane Reductions to facilitate hydro utility relocation at the East Service Road

 

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Read more »

May 012019

Updated: Overnight Road Decking Repair at Cedarvale Station – May 3, 2019

Originally Posted: April 24, 2019 

Updated: May 1, 2019 

What Work is Taking Place?

To accommodate the repair of road decking on Eglinton Avenue West, crews will be working during early morning hours (2:00 a.m. – 5:00 a.m.) on May 3rd, 2019 to minimize reduce the risk of incident to crew members and impacts to traffic.

Read more »