April 252017

NOTICE OF UPCOMING PARKING CHANGES AT KENNEDY STATION PHASE 1 AS EARLY AS MAY 2017

Kennedy Station will be the terminal station at the eastern end of the Eglinton Crosstown LRT line. Kennedy Station is yet another station along the LRT line to serve as a Mobility Hub, with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and the TTC bus terminal.

 

What Work is Taking Place? Read more »

April 242017

Mount Dennis Rail Corridor Work

Mount Dennis Rail Corridor Work

Monday April 24 to Monday May 22, 2017 

  Read more »

April 242017

Cedarvale Station Utilities Relocations

Original Issue Date: April 24, 2017
Updated: August 10, 2017 

What work is taking place?

To make way for the future Cedarvale interchange station, work will commence to replace and relocate existing utilities in the area of Allen Road and Eglinton Avenue West. Work is permit pending. Read more »

April 202017

UPDATE: Demolishing the Abandoned TTC Bus Depot

What Work is Happening?

  • The abandoned TTC Bus Depot (pictured below) is being demolished to make way for the new Eglinton LRT Station’s primary entrance (pictured at bottom) and new developments at Yonge and Eglinton.

Progress to Date

  Read more »

April 202017

Dewatering System at Laird Station

Installation of the dewatering system designed for Laird Station is underway and surface installations will begin as early as late April 2017. Dewatering systems involve controlling groundwater by pumping to locally lower groundwater levels in the vicinity of the excavation.  The specific dewatering system for each station is selected based on local soil conditions as well as existing groundwater levels.  Read more »

April 202017

Decommissioning and Bell Utility Works at Brentcliffe Road Launch Shaft Site

Over the last few months, the tunnel contractor has begun decommissioning the Launch Shaft site at Brentcliffe Road to make way for the station contractor. There will be no change to the footprint of the site. However, as tunnel work has concluded, preparatory works will now begin for the next phase of LRT construction. Read more »

April 192017

Dewatering System at Avenue Station

 

Dewatering System at Avenue Station

  Read more »

April 192017

Line Painting at Avenue Station

 

Line Painting at Avenue Station

  Read more »