January 152018

Updated: Ventilation Fan Works at Laird Station

Original Issue Date: December 18, 2017

What Work is Taking Place?

Starting as soon as mid-January 2018, crews will complete electrical connections for ventilation fans within the existing tunnels underneath Eglinton Avenue. Read more »

January 122018

Overnight Monitoring Installations Around the TTC Eglinton West Station Bus Loop

WHAT WORK IS TAKING PLACE?

Geotechnical monitoring instruments are installed in the vicinity of the station construction to monitor the ground conditions as construction is underway. 

Monitoring instruments are regularly checked to measure any movements of the ground and assess if there is a need for additional measures. 

The majority of the monitors for Cedarvale Station were installed in late 2016/early 2017. Read more »

January 102018

Kennedy Station North Entrance Demolition and Pedestrian Tunnel Closure

Kennedy Station will be the terminal station at the eastern end of the Eglinton Crosstown LRT line. Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure.  

What Work is Taking Place? Read more »

January 102018

Overnight Sanitary Sewer Line Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are installing a new sanitary sewer system along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  As part of this work, diversion of the existing sanitary sewer service line is required on several occasions over the course of the work.  Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new sanitary sewer infrastructure is installed. Read more »

January 092018

Overnight Preparatory Works for Sewer Lining at Oakwood Station

 

In advance of upcoming mining works at Oakwood Station, crews must install sewer linings to the existing sewer infrastructure on Eglinton Avenue West between Oakwood Avenue and Times Road. Work also includes one location on Times Road, just north of Eglinton Avenue.  Read more »

January 092018

Overnight Preparatory Works for Sewer Lining at Oakwood Station

 

In advance of upcoming mining works at Oakwood Station, crews must install sewer linings to the existing sewer infrastructure on Eglinton Avenue West between Oakwood Avenue and Times Road. Work also includes one location on Times Road, just north of Eglinton Avenue.  Read more »

January 082018
January 082018
January 052018

Rescheduled: Overnight Sanitary Sewer Relocation at Brentcliffe Portal January 9th to 14th from 9:00 p.m. to 5:00 a.m.

Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018 

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place? Read more »