May 102017

Ongoing Preparatory Works between Brentcliffe Road and Midland Avenue: Street Furniture Removals SPRING & SUMMER 2017

What Work is Taking Place?

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Brentcliffe Road and Midland Avenue. Read more »

May 102017

Traffic Reconfiguration at Don Mills & Eglinton: Nighttime and 24 Hour Weekend Work May 11 – 14

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as May 11, 2017.  Read more »

May 092017

Shoring and Excavation Work Continues for Laird Station: Long Term Sidewalk Closure

Since June 2016, shoring and excavation work has been underway within the main and secondary entrance sites for the future Laird Station. Read more »

May 052017

Upcoming Support of Excavation and Utility Relocations in the Roadway at Mount Pleasant Station

In Fall 2016, crews started support of excavation (shoring) works at both the Main and Secondary Entrance sites of the future Mount Pleasant Station. The next step is to begin utility relocations and shoring of the station box in the roadway. Crews will complete work on the north side of Eglinton Avenue East first, then flip to the south side. Read more »

May 032017

Hydro Works at Leaside Station

What Work is Taking Place

Crews will perform work on a hydro cable chamber located within the Bayview and Eglinton intersection. All left turns at the intersection will be temporarily prohibited during the work.