Don Mills Road

Looking for updates near a specific intersection?

Choose an intersection from the drop down list to view all of the latest news and construction updates in that area. Intersections are listed from west to east with Eglinton as the main cross-street.




Syndicate content
 
April 102017

Line Painting Refresh for Science Centre Station

What Work is Taking Place?

Crews will refresh the existing line markings in all directions in the vicinity of the intersection on Eglinton Avenue East and Don Mills Road.

Timing Read more »

March 072017

UPDATE: Traffic reconfiguration in support of excavation works and utility relocations for Science Centre Station

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East was reconfigured in mid-February 2017. This new set up will remain in place for up to three (3) months. Read more »

February 082017

Early Morning Work for Science Centre Station

What Work is Taking Place?

A large drill rig will be moved from the work zone on the south side of Eglinton Avenue East, east of Don Mills Road, to the northeast corner of Eglinton Avenue East at Ferrand Drive. The drill rig is required for piling work in support of the future Science Centre Station. Read more »

February 072017

UPDATE: Traffic reconfiguration in support of excavation works and utility relocations beginning February 17 for Science Centre Station

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as February 17, 2017. Read more »

January 302017

UPDATE: Weekend Lane Reductions and Turn Restrictions For Hydro Ductbank Inspections at Science Centre Station 

What Work is Taking Place?

As part of ongoing utility relocation work for the future Science Centre Station, crews will be conducting hydro infrastructure investigations in the vicinity of Don Mills Road and Eglinton Avenue beginning as early as January 30, 2017.  Read more »

December 222016

Overnight Work for Science Centre Station

What Work is Taking Place?

A large drill rig will be moved from the secondary entrance on the northeast corner to the south side of Eglinton Avenue East at Ferrand Drive. The drill rig is required in preparation for piling work in support of the future Science Centre Station.

Timing Read more »