Clearing, Grubbing, and Pruning between Don Avon Drive to Victoria Park Avenue in Preparation for Construction of Surface Stops

As our constructors get ready to ramp up construction activity at the surface section of the Eglinton Crosstown LRT project, clearing, grubbing, and pruning and protection activity continues as part of preparatory work. This activity commenced two years ago and is done on an ongoing, as-needed basis to support the construction of the Eglinton Crosstown Light Rail Transit Project (ECLRT). All works will be carried out with the approvals and cooperation of the responsible authority. Read more »

March 092018

Overnight Road Repair Work Starting March 12 - Traffic Lane Reductions at Don Mills & Eglinton

What Work is Taking Place?

Ongoing road maintenance continues around the Don Mills Road and Eglinton Avenue East intersection. The rebuilding of catch basins on Eglinton Avenue East between the DVP and Don Mills Road will start on Monday, March 12, 2018 for approximately one week.

To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight.

Hours of Work Read more »

March 062018

LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station

What Work is Taking Place?

Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station.

Starting in mid-March for approximately three (3) weeks, work to connect the new watermain section to the existing infrastructure will take place. During these works, residents in the catchment area may experience lower than normal water pressure. Read more »

March 022018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:

Read more »

February 272018

Overnight Piling Work February 28 for Science Centre Station

What Work is Taking Place?

Crews will be drilling piles within the Don Mills Road and Eglinton Avenue East intersection as part of the Support of Excavation work at the future Science Centre Station. 

Due to the location of the piles and in an effort to minimize disruption to local traffic and commuters work will be performed overnight on Wednesday, February 28, 2018 from 8:00 p.m. to 5:00 a.m. Thursday morning. The intersection will be restored in advance of morning rush hour. Read more »

January 222018

Upcoming Traffic Changes at Don Mills and Eglinton

Upcoming Work and Construction Staging: January 2018

As part of the continued support of excavation works and utility relocation works for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as late January 2018.  Read more »

January 122018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on January 11, 2018. You can see the presentation here:

Read more »

November 222017

Hydro Ductbank Connection Works at Ferrand Drive for Science Centre Station

Re-issued: November 22, 2017
Updated: September 28, 2017
Original Issue Date: August 3, 2017

What Work is Taking Place? Read more »

November 212017

Overnight Stormwater/Sanitary Relocation for Science Centre Station: Eglinton Lane Reductions & Closure of Ferrand Drive

What Work is Taking Place?

Crews will relocate an existing stormwater line on the north side of Eglinton Avenue East from just west of Don Mills Road to approximately Gervais Drive and make connections to existing infrastructure on the south side of Eglinton to support the upgrade of existing water infrastructure at the future Science Centre Station. In an effort to minimize disruption to local traffic and commuters, work will be performed overnight in stages. Read more »