November 112016

Next Stage of Utility Relocations for Science Centre Station

Beginning as early as Sunday, November 13 work zones will be erected within the roadway at both the northwest and southwest corners of Don Mills Road and Eglinton Avenue East as crews will continue to relocate existing utilities in the vicinity of Don Mills Road and Eglinton Avenue East. Read more »

November 082016

UPDATED: Overnight Line Painting for Science Centre Station Starts Friday, November 11, 2016

UPDATED
Overnight lane reductions on Don Mills Road and on Eglinton Avenue East will be required begining on Friday, November 11 for approximatley 3 nights as crews remove existing line markings on the roadway then repaint in preparation for station construction at the future Science Centre Station. 

What to Expect Read more »

November 042016

Updated: Ferrand Drive Roadwork and Sidewalk Closure for future Science Centre Station

What Work is Taking Place?

  • To prepare for the future construction of Science Centre Station, crews will remove existing curbs on the north side of Ferrand Drive in the Don Mills Road and Eglinton Avenue East vicinity. Following the curb removal, crews will install a new curb wall.

Windom Rd Read more »

October 142016

Road Widening and Sidewalk Closure for future Science Centre Station

What Work is Taking Place?

To support construction of the future Science Centre Station, work will commence to widen sections of Eglinton Avenue East from west of Don Mills Road to the Don Valley Parkway.  Read more »

October 062016

Telecommunication Utilities Relocation for Science Centre Station

What Work is Taking Place?

In October 2016, crews will begin relocation of existing telecommunication lines in the vicinity of Don Mills Road and Eglinton Avenue East.  Telecommunication lines within man holes as well within pre-existing duct banks will be relocated in preparation for station construction.  All work conducted during this phase will occur within the public boulevards.  Read more »

September 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Read more »

August 172016

Watermain Relocation for Science Centre Station

What Work is Taking Place?

A section of the existing watermain will be replaced on Eglinton Avenue East just east of Don Mills Road.

Timing