Science Centre Station Open House

Thank you for attending our Science Centre station open house on July 11, 2016. 

For those of you who missed it, the presentation is here:

 

June 172016

Enbridge Gas Distribution Line Relocation for Science Centre Station

What work is Taking Place?

  • To accommodate the new Eglinton Crosstown, Enbridge is required to relocate a gas line.
  • Work will start as early as June 20, 2016 and last for approximately six weeks.

Timing Read more »

June 032016

Disruption from service locomotives

Dear Neighbour, 

As you may know, the Eglinton Crosstown LRT Project includes a 10-kilometre underground portion. Two Tunnel Boring Machines (or “TBMs”) are building the 3.5km eastern underground section of the Crosstown tunnels between Brentcliffe Road and Yonge Street. The TBMs are making great progress tunneling at an average rate of over 10-15 metres per day.  They have completed approximately 70% of their journey and expected to be at Yonge Street in early September. Read more »

May 092016

Update: Geotechnical Works continue along Eglinton Avenue East

What work is starting?

In February 2016, crews began conducting preparatory activities in the Eglinton Avenue East vicinity to make way for the future Eglinton Crosstown LRT. 

Upcoming works – geotechnical testing   Read more »

January 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Read more »