Dufferin Street

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
August 132014

Short Term Sewer Rehabilitation Work on Eglinton Avenue at Marlee Avenue

What we are building

What: Crews will be performing limited sewer rehabilitation work as part of construction activity for the extraction shaft and the tunnelling. 

Where: Eglinton Ave from west of Alameda Avenue to just east of Marlee Avenue.  Read more »

August 052014

Short Term Lane Closures along Eglinton Avenue West for Monitoring Equipment Installation Black Creek Drive -Yonge Street Summer 2014 - Summer 2015

What work is starting?

What: Crews will be installing ground movement monitoring equipment.
 
Why: Monitoring equipment will provide information on the ground conditions during excavation and tunnelling activities to the construction team. Read more »

June 182014

Closure of Dynevor Road for Headwall Construction at Dufferin

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today.

What we are building

When: Dynevor Road will be closed as early as mid June for several months.Timelines may be rescheduled or adjusted due to weather conditions and unforeseen circumstances. Read more »

June 022014

Construction of Emergency Exit Building - Update for Eglinton Avenue West & Little Blvd

The Eglinton Crosstown is a transit project that will provide rapid and reliable service across Eglinton Avenue. It includes an underground central section from Keele Street to Don Mills Road, bringing transit service that will be up to 60% faster than bus service today. Read more »

June 022014

Construction Update for June 2014

Utility relocation and headwall construction along Eglinton Avenue West between Caledonia and the Allen Road area began in March 2013. Many works along the road have been completed and other on-going works are progressing well. The Crosstown Team appreciates the patience of our neighbours while we build transit.

Crosstown alignment Read more »

May 262014

Dufferin Station Utility Relocation and Headwall Construction - Traffic switch to South Side of Eglinton Ave

Starting as early as the first week of June  The Eglinton Crosstown is a transit project that will provide rapid and reliable service across Eglinton Avenue. It includes an underground central section from Keele Street to Laird Drive, bring transit service that will be up to 60% faster than bus service today. Read more »