   What Work is Taking Place?

  • Ongoing piling activities for construction of the abutments of the Elevated Guideway.
  • Work will be taking place between Keelesdale Park Drive and Black Creek Drive on the north side of Eglinton Avenue West.

 

work zone for piling

 

Hours of Work

  • This work will occur between the hours of 7:00 a.m. and 11:00 p.m. until mid-January 2018
  • If overnight work is required, we will notify the public in advance and monitor activities throughout.
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.

 

What to Expect

  • Nearby businesses and residents can expect vibration and noise from a diesel hammer pile driving rig, a mobile crane and other construction equipment.

 

Traffic/Pedestrian Details

 ·   Black Creek Drive will be down to one northbound lane from the intersection at Eglinton Avenue West to the intersection at Todd Bayliss Drive.

 ·     Pedestrian access at the intersection and on the southside of Eglinton Avenue West will remain open.

For more information, please contact Lancefield Morgan at the West Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

 

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.