February 082017

Early Morning Work for Science Centre Station

What Work is Taking Place?

A large drill rig will be moved from the work zone on the south side of Eglinton Avenue East, east of Don Mills Road, to the northeast corner of Eglinton Avenue East at Ferrand Drive. The drill rig is required for piling work in support of the future Science Centre Station. Read more »

December 222016

Overnight Work for Science Centre Station

What Work is Taking Place?

A large drill rig will be moved from the secondary entrance on the northeast corner to the south side of Eglinton Avenue East at Ferrand Drive. The drill rig is required in preparation for piling work in support of the future Science Centre Station.

Timing Read more »

December 122016

Overnight CCTV Investigations along Eglinton Avenue East

What Work is Taking Place?

Crews will be conducting CCTV investigations of the storm and sanitary sewer lines along Eglinton Avenue East. Crews will access all manholes in the roadway along Eglinton Avenue East between Midland Avenue and Laird Drive, along Transway Crescent at Kennedy Station and from approximately 50-100 meters north at all intersections to determine the condition of existing storm and sanitary lines. 

Hours of Work Read more »

November 302016

UPDATE: Access to Ferrand Drive from Eglinton Avenue Closed Dec. 5 & 6

What Work is Taking Place?

Crews will be grading and paving on Eglinton Ave East along Ferrand Drive to prepare for the future construction of Science Centre Station. To complete the work, access to Ferrand Drive from Eglinton Avenue East will be closed.

Timing Read more »

November 162016

Update: Hydro Utility Relocations for Science Centre Station: Pedestrian Crosswalk Closure and TTC Bus Detour

What Work is Taking Place?

In mid-November crews began to set-up work zones within the roadway at both the northwest and southwest corners of Don Mills Road and Eglinton Avenue East as crews continue to relocate existing utilities at the intersection. Work began on relocating hydro utilities and work continues on relocating telecommunication lines within man holes as well within pre-existing duct banks in preparation for station construction.  Read more »

November 112016

Next Stage of Utility Relocations for Science Centre Station

Beginning as early as Sunday, November 13 work zones will be erected within the roadway at both the northwest and southwest corners of Don Mills Road and Eglinton Avenue East as crews will continue to relocate existing utilities in the vicinity of Don Mills Road and Eglinton Avenue East. Read more »