November 082018

Hydro Pole and Duct Bank Installation Work at South Service Road at Kennedy Station

What Work is Taking Place?

In support of construction of the future Kennedy Station, crews will be conducting hydro pole and duct bank installation at the South Service Road. The work will begin as early as Friday, November 9th, and lasting for approximately two (2) weeks.

Read more »

October 312018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:

Read more »

October 192018

North Passenger Platform and Bus Loop Restoration at Kennedy Station

What Work is Taking Place?

Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Read more »

October 122018

Update: Upcoming Traffic Changes at Kennedy and Eglinton Intersection in Support of Shoring Work

Originally Published: October 12, 2018

Updated: October 19, 2018

Updated: October 26, 2018

Updated: October 29, 2018

Updated: November 5, 2018 Read more »

October 112018

Large Tower Crane Delivery and Installation at Kennedy Station

What Work is Taking Place?

On Tuesday, October 16, 2018 a large tower crane will be delivered to Kennedy Station in advance of deep excavation works. The tower crane will be erected at Compound 2, within the existing construction zone at Kennedy Station (adjacent to Transway Crescent). 

The tower crane will be erected on the concrete base (pictured below). Delivery and set-up will take one day to complete.   Read more »

September 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:

Read more »

September 112018

Installation of Temporary Traffic Signals at North Service Road at Kennedy Station

Originally Published: September 11, 2018

Updated: October 10, 2018

What Work is Taking Place?

In support of construction of the future Kennedy Station, crews will be installing new traffic signals 160m east of Kennedy Road and Eglinton Avenue East. Read more »

September 072018

Upcoming Traffic Changes at Kennedy and Eglinton Intersection in Support of Shoring

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in September.

Shoring began in April 2018 and will continue in phases at the intersection. Read more »

September 052018

UPDATED: Support of Excavation Works at the North End of Kennedy GO Station Platform as Part of Eglinton Crosstown LRT

What Work is Taking Place?

As part of continued support of excavation works (shoring) for the future Kennedy Station, crews will continue work on the north end of the GO platform as part of the GO Transit improvements.

To facilitate these improvements, installation of support of excavation are also being made to the GO Transit Stouffville Corridor at Kennedy GO Station starting as early as Saturday, September 8, 2018. Read more »

August 292018

UPDATE: Watermain, Storm and Sanitary Relocation at Kennedy Station Ionview Road to Kennedy Road

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between Ionview Road and Kennedy Road.

 Crews continue to work on installing the new storm and sanitary system from Ionview to Kennedy and will complete their work with a final connection to the existing manholes located within the Kennedy and Eglinton intersection. Read more »