October 012020

Updated: Extended Hours at Laird Station (24 hour work) - September 30, 2020

What Work is Taking Place?

As early as September 30, 2020, permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday for approximately five (5) weeks. The current extended hours (6:00 a.m. -1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year.

September 102020

Laird Station Extended Hours - September 14, 2020

September 14, 2020

What Work is Taking Place?

Beginning September 14, 2020, crews will begin working extended hours at Laird Station to accommodate concrete and formwork activities in the tunnel and entrance shafts.

What to Expect Read more »

September 092020

Laird Station Concrete Chipping Works - September 10, 2020

Monday September 14 –  Friday September 18, 2020

What Work is Taking Place? Read more »

September 092020

Laird Station Concrete Pour - September 10, 2020

September 10, 2020

What Work is Taking Place?

Beginning September 10, 2020, crews will perform a concrete pour at the main entrance at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m.

What to Expect Read more »

August 062020

Sidewalk and Lane Closure at Laird Station Friday August 7, 2020

What Work Is Taking Place?
On Friday August 7, 2020, crews will perform a concrete pour at the Laird Station Main Entrance site.  The work will be performed using a mobile crane and several concrete trucks.  The eastbound curb lane on Eglinton Avenue East, the south sidewalk in front of Laird Station Main Entrance as well as the west and south crosswalks at Laird Drive and Eglinton Avenue East will be closed while this work takes place.  Upon completion of the pour, the lane, sidewalk and crosswalks will re-open. Read more »

Categories:
July 272020

Laird Station 24-Hour Concrete Pour

What Work is Taking Place?
Beginning July 29, 2020, crews will perform a 24-hour concrete pour at the main entrance at Laird Station. Work will begin preparatory work as early as 5:00 a.m. and the pour will be ongoing for approximately 24 hours.  

  Read more »

Categories:
June 252020

Decommissioning Monitoring Wells - Zone 8 - Laird to Brentcliffe

 

Decommissioning Monitoring Wells between Laird Drive and east of Brentcliffe Road Read more »

June 162020

Laird Station Construction Updates

LAIRD STATION CONSTRUCTION UPDATE

JUNE 2020 Read more »

June 152020

24 Hour Concrete Pour - Laird Station

 

LAIRD STATION

24-HOUR CONCRETE POUR Read more »

June 012020

Concrete Pour at Laird Station

CONCRETE POUR AT LAIRD STATION