Lebovic Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
February 282018

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on February 27, 2018. You can see the presentation here: 

Read more »

February 042018

Resumption of Telecommunication Utilities Relocation: Eglinton Square to Birchmount Road

What Work is Taking Place?

  • Crews will resume the relocation of existing telecommunication lines along Eglinton Avenue East, between Victoria Park Avenue and Birchmount Road.
  • Telecommunication lines within utility chambers as well within pre-existing duct banks will be relocated in preparation for surface stop construction.

Hours of Work

  • Work began late October 2017 and will begin again a
January 312018

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on January 30, 2018. You can see the presentation here:

December 062017

East At-Grade (Pharmacy Stop to Ionview Stop) and Kennedy Station Open House

Thank you for attending the open house about Kennedy Station and East At-Grade (Pharmacy Stop to Ionview Stop) on December 5, 2017. 

For those of you who missed it, the presentation is here: Read more »

November 062017

Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

Updated: November 6, 2017

Original Post: October 20, 2017

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Read more »

October 202017

Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Read more »

September 282017

UPDATED: Ongoing Preparatory Works between Leslie and Midland: Street Furniture Removals

Updated: September 28, 2017
Original Issue Date: May 10, 2017

What Work is Taking Place? 

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Leslie Street and Midland Avenue. Read more »

September 272017

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on September 26, 2017. You can see the presentation here: Read more »

August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »