October 05 2018

Black Creek Closures and Overnight Work for West Portal & Elevated Guideway Girder Installations

As part of the ongoing works on the West Portal & Elevated Guideway, over a two night period crews will be installing a duct bank across Black Creek Drive on October 12-14 and 19-21, 2018. Black Creek Drive southbound and northbound will be closed one at a time as follows to safely carry out the work:  Read more »

October 04 2018

Green Wall Construction Continues at the E.T. Seton Park

What Work is Taking Place?

As part of the continued construction of the future Sunnybrook Park Stop, crews will continue construction of a green wall (retaining wall) at the E.T. Seton Park along the south side of Eglinton Avenue East at Leslie Street intersection as part of the construction of the Eglinton Crosstown LRT. Read more »

October 04 2018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:

Read more »

September 25 2018

Support of Excavation Work at Eglinton Station between Cowbell Lane and Dunfield Avenue

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation.  

The next phase (depicted below) will occur on the south side of Eglinton Avenue East from Cowbell Lane to Dunfield Avenue and will take approximately 3-4 months to complete. 

 

Hours of Work Read more »

September 25 2018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:

Read more »

September 25 2018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting wet utilities relocation work along Eglinton Avenue East between Warden Avenue and Birchmount Road. Read more »

September 25 2018