Mount Pleasant Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
August 142018

Storm Sewer Installation Work at Taunton Rd Resuming Mt. Pleasant Station

What Work is Taking Place?

Since last year, crews have been completing storm sewer installation on Eglinton Avenue East at Taunton Road and Brownlow Avenue.  Storm sewer installation and connection work at the Brownlow Avenue site is now complete.  Work at the Taunton Road site has been on hold temporarily while the new manholes are designed and procured.  It will resume as early as Wednesday August 15 and is expected to continue through October 2018.  Read more »

August 142018

Storm Sewer Installation Work at Taunton Rd Resuming Mt. Pleasant Station

What Work is Taking Place?

Since last year, crews have been completing storm sewer installation on Eglinton Avenue East at Taunton Road and Brownlow Avenue.  Storm sewer installation and connection work at the Brownlow Avenue site is now complete.  Work at the Taunton Road site has been on hold temporarily while the new manholes are designed and procured.  It will resume as early as Wednesday August 15 and is expected to continue through October 2018.  Read more »

July 202018

Construction Notice - Leaside Station - Overnight Line Painting

Overnight Line Re-Painting at Leaside Station

 

WHAT WORK IS TAKING PLACE?

Leaside station crews will complete a refresh of some of the crosswalks and lines in around the Bayview Ave and Eglinton Ave E intersection. Due to the volumes of traffic in the area and existing construction set up reducing available lanes, these works will be completed overnight. Read more »

July 182018

Construction Notice - Overnight Wet Utilities Work at Mount Pleasant Station onThursday July 19

 

Overnight Wet Utilities Work at Mount Pleasant Station

What Work is Taking Place? Read more »

Categories:
July 172018

Construction Notice - Tentative Overnight Work at Mount Pleasant Station - July 19, 2018

Planned Overnight Work at Mount Pleasant Station

Thursday July 19, 2018*

 

 What Work is Taking Place?

On Thursday July 19, 2018 from 8:00 p.m. overnight to Friday morning at 6:00 a.m. Eglinton Avenue will be reduced to one shared lane of traffic between Mt. Pleasant Road westward toward Brownlow Avenue Read more »

July 132018

Construction Notice: Support of Excavation at Mount Pleasant Station

 

Support of Excavation at Mount Pleasant Station  

 

What Work is Taking Place? Read more »

July 112018

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on July 10, 2018. You can see the presentation here:

Download the presentation

June 222018

Notice of Planned Overnight Water Shut-off Monday June 25, 2018

What Work is Taking Place?

On Monday June 25, crews will conduct a water shut-off as part of ongoing construction works at Mount Pleasant Station.  To minimize the impact to affected properties, this work will be carried out overnight.

Water Shut-off Details Read more »

June 212018

Brownlow Avenue Closure and Overnight Work for Storm Sewer Connection

What Work is Taking Place?

Since last year, crews have been completing storm sewer installation on Eglinton Avenue East at Taunton Road and Brownlow Avenue.  Installation of the sewer pipe is complete, now crews must connect the new infrastructure to new and existing manholes.  Read more »