April 02 2019

Daytime Concrete Pour at Fairbank Station - April 3, 2019

What Work is Taking Place?

On Wednesday April 3, crews will perform a concrete pour at the Main Entrance area of Fairbank Station. The concrete will form part of the Main Entrance walls.  A concrete pump will be placed on Vaughan Road behind the Main Entrance site, and concrete trucks will deliver concrete to the site.  Dufferin Street and Eglinton Avenue West will remain open while work takes place.

Hours of Work Read more »

April 02 2019

Water Shut-off for Watermain Reinstatement Work at Taunton Road April 4, 2019

What Work is Taking Place?

On Thursday April 4, 2019, there will be a water shut-off starting at 9:00 a.m. for approximately seven (7) hours while crews perform watermain connection work at Eglinton Avenue East and Taunton Road.  This activity is required to complete the ongoing watermain reinstatement work.  Due to the equipment required to perform this activity, such as a hydro-vacuum truck, this shut-off will be conducted during the day.  Affected properties are listed below. Read more »

April 01 2019
April 01 2019

Extended: Sidewalk Closure for Civil Road Work between Pharmacy Avenue and Lebovic Avenue

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue.  Work began in February 2019 and will be extended until the end of April 2019.

There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work.

Hours of Work Read more »

April 01 2019

Traffic Restrictions at Bermondsey Road and Sloane Avenue at Eglinton Avenue East

Latest Update: April 17, 2019

WHAT WORK IS TAKING PLACE?

Throughout 2019, Eglinton Crosstown LRT construction requires temporary changes to intersection operations from Credit Union to Ionview for road paving and guideway construction. This work is required for the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East. Read more »

March 29 2019

Proposed Leslie Street Closure - Backgrounder

Crosslinx Transit Solutions is seeking approvals for temporary traffic restrictions at Leslie Street in July and August 2019.  

You are invited to attend the Town Hall meeting on April 4, 7:00pm – 8:30pm at the Japanese Canadian Cultural Centre, 6 Garamond Court, to learn more about what is proposed and to provide your input.

What’s being proposed? Read more »

March 29 2019

Construction Notice: Overnight Utilities Relocations at Birchmount Road

OVERNIGHT UTILITIES RELOCATIONS AT BIRCHMOUNT ROAD AND EGLINTON AVENUE EAST

 

WHAT WORK IS TAKING PLACE?

 

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

  Read more »

March 29 2019

Western Segment Open House

Thank you for attending the Western Segment Open House on March 28, 2019. For those of you who missed it, the presentation is here:

Download the presentation

March 29 2019

Telecommunication Relocations at Wynford Bridge

 

Telecommunication Relocations at Wynford Bridge  

WHAT WORK IS TAKING PLACE? Read more »