September 13 2019

Emergency Weekend and Overnight Bell Work at Mount Pleasant Station Friday, September 13, 2019

What Work is Taking Place?

Starting Friday September 13, crews will work through the weekend and overnight to perform emergency Bell utility work on the south side of Eglinton Ave E. Construction activities include excavation and cable repair work. This work requires the use of excavators, hydro-vacuum trucks and generators, as well as site lighting. This work will take place within the existing work zone. Crews will endeavour to minimize disruption as much as possible. Read more »

September 13 2019

Temporary Traffic Change for Wet Utility Work at Chaplin Station September 16 – 24, 2019

On September 16, a temporary change will be implemented on Eglinton Avenue, east of Chaplin Crescent to accommodate wet utility work for Chaplin Station.  The northeast work zone will be extended further east and south of Latimer Avenue.  Traffic on Eglinton Ave will be shifted south.  No changes to pedestrian routes are anticipated.  Once the work is complete, the work zone will return to the current configuration.

Upcoming Traffic and Pedestrian Configuration Read more »

September 12 2019
September 11 2019

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on September 10, 2019. You can see the presentation here:

Read more »

September 11 2019

Update: North Driveway Closure at 2300 Eglinton Avenue East for Work at Massey Creek

Original Post: August 28, 2019

Updated: September 11, 2019

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work will continue for approximately 4 months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

September 11 2019

Permanent Westbound Left Turn Lane Removal – Pharmacy Avenue

What Work is Taking Place?

In order to accommodate the future Pharmacy Stop construction, the westbound left turn lane (to southbound) will be removed at the Pharmacy Avenue and Eglinton Avenue East intersection as early as September 16, 2019.   Read more »

September 11 2019

Extension of the Secondary Entrance Work Zone Friday September 13, 2019

As early as Friday September 13, the secondary entrance work zone will be extended eastward, approximately three (3) metres from 300 Eglinton Avenue E to accommodate ongoing construction activities at Mount Pleasant Station. All protection barriers and fences surrounding the work zone will be maintained. This configuration will be in place until approximately late October 2020. Read more »

September 10 2019

EARLY MORNING CONCRETE POURS: CELESTICA BRIDGE AND DON VALLEY PARKWAY WEST

 

EARLY MORNING CONCRETE POURS: CELESTICA BRIDGE AND DON VALLEY PARKWAY WEST

WHAT WORK IS TAKING PLACE? Read more »