September 25 2019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:

 

Download the presentation

September 25 2019

Tower Crane Removal at Science Centre Station

Tower Crane Removal at Science Centre Station

WHAT WORK IS TAKING PLACE? Read more »

September 25 2019

Tertiary Entrance Excavation Update at Chaplin Station

Information as of August 22, 2019

Excavation continues at the Chaplin Station Tertiary Entrance site, located on the south side of Eglinton Avenue, east of Chaplin Crescent, beside the former Toronto Fire Hall.  Excavators dig and remove soil from the work zone.  Excavated material will be transferred into dump trucks and hauled to an off-site facility.  Installation of tie-backs will take place from within the site as excavation progresses.  Excavation will begin at 6:00 a.m. on weekdays.

DETAILS Read more »

Categories:
September 20 2019

CANCELLATION NOTICE: Berwick Avenue Road Closures for TTC Line 1 Facility Service Building Construction September 20 – 23, 2019

Please be advised that the Berwick Avenue closure scheduled for Friday September 20, 2019 has been cancelled and has been rescheduled for one weekday between September 30 and October 11, 2019.  A subsequent notice will be issued once the reschedule date has been confirmed

 

Road Closure Details

The Berwick Ave closure scheduled for Friday September 20 – Monday September 23, 2019 has been cancelled.

 

Berwick Ave will be closed between Duplex Ave and Yonge St: Read more »

September 18 2019

Partial Driveway Closure - 2300 Eglinton Avenue East

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will continue work with stage 2 at Massey Creek. As early as September 20th the eastern driveway at 2300 Eglinton Avenue property will be closed for four (4) months. The closure is required to carry out the construction works in a safe and prompt manner. 

During the closure, vehicles will be directed to use the accessible western driveway along Eglinton Avenue. This can be seen in the figure below: Read more »

September 16 2019

DECK MAT REPAIR - LEASIDE STATION

Six (6) additional days are required for deck mat repair at Leaside Station. On September 19/20, September 26/27 and October 3/4 between 7:00am - 7:00pm there will be lane and turn restrictions on Eglinton Avenue East at Bayview Avenue to complete decking repairs.

TRAFFIC AND PEDESTRIAN IMPACTS Read more »