July 17 2019

Extension of Berwick Avenue Road Closure for TTC Line 1 Facility Service Building Construction - July 16 – 22, 2019

On July 5, 2019, Berwick Avenue closed between Duplex Avenue and Yonge Street to perform supporting construction activities for TTC’s Line 1 Subway Facility Services Building.  Followed by two weekend closures from July 19 – 22, 2019, and July 26 – 29, 2019.  An extension of the first closure, from July 15 – 19, 2019 is required due to longer than anticipated work times.


Road Closure Details Read more »

July 17 2019

UPDATE: CROSS PASSAGE 10 AT LILLIAN STREET

Underground excavation work will commence in early August in the tunnels below Eglinton Avenue East at Lillian Street. This work will occur on a 24 hour basis with all works being completed below ground. The excavation will create a connection corridor underground between the north tunnel and the south tunnel. The work is expected to last for approximately two (2) weeks.   Read more »

July 16 2019

Updated Traffic Configuration: Swift and Credit Union Drive at Eglinton Avenue East

ORIGINAL POST: JULY 11, 2019

UPDATED: JULY 17, 2019

WHAT WORK IS TAKING PLACE? Read more »

July 15 2019

GUIDEWAY CONSTRUCTION ON EGLINTON AVENUE EAST AT THE DON VALLEY PARKWAY

 

ORIGINAL POST: JULY 5, 2019

Last update: July 11, 2019

UPDATED: JULY 15, 2019

GUIDEWAY CONSTRUCTION ON EGLINTON AVENUE EAST AT THE DON VALLEY PARKWAY Read more »

July 15 2019

Guideway Work at Warden Avenue

What Work is Taking Place?

As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at Warden intersection at Eglinton Avenue East. As early as July 29, 2019 the construction zone will shift to the center of Eglinton Avenue East at Warden Avenue and be in place for approximately six (6) weeks. There will be no through north-south traffic on Warden and left turn restrictions at the intersection. Read more »

July 15 2019

Updated: Guideway Construction On Eglinton Avenue East at Wynford Drive

ORIGINAL POST: JUNE 19, 2019

Last update: July 12, 2019

UPDATED: JULY 15, 2019 Read more »

July 12 2019

Street Light Installations on Eglinton Avenue East at Jonesville Crescent

 

Street Light Installations on Eglinton Avenue East at Jonesville Crescent   Read more »

July 12 2019

Early Work at Forest Hill Station - Saturday July 13, 2019

What Work is Taking Place?

Crews will pour concrete at the Secondary Entrance site of Forest Hill on Saturday July 13, 2019.  To ensure the integrity of the concrete, crews will begin work at 5:00 a.m., avoiding peak temperatures. Work will take place within existing construction zones.