Pharmacy Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
March 132019

Extended: Sidewalk Closure for Civil Road Work between Pharmacy Avenue and Lebovic Avenue

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue.  Work began in February 2019 and will be extended until the end of March 2019.

There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work.

Hours of Work Read more »

March 132019

Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue.  Read more »

March 072019

Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

February 282019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

February 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Read more »

February 192019

Overnight Temporary Traffic Diversion to Facilitate Sub-Surface Infrastructure for Future Traffic Signals at Eglinton Square

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be installing the conduits for the permanent traffic signals at Eglinton Square. Starting as early as Wednesday, February 20, 2019 until Thursday, February 21, 2019. The work will taking place during the overnight period. Read more »

February 122019

Sidewalk Closure between Pharmacy and Lebovic for Civil Road Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue.

There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work, beginning as early as Monday February 18, 2019 for approximately one (1) month. Read more »

February 052019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

January 182019

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

Telecom work has been extended until the Spring 2019.

Read more »

January 152019

Duct Bank Concrete Pour of Guideway Between Eglinton Square to Pharmacy Avenue

Last Updated: January 24, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »