Pharmacy Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
March 252019

Weekend Intersection Paving Traffic Restriction at Pharmacy Avenue

Latest Update: March 27, 2019

What Work is Taking Place?

As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East between Victoria Park Avenue and Birchmount Road in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at the Pharmacy Avenue intersection along Eglinton Avenue East. Read more »

March 222019

Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue.  Read more »

March 212019

Updated: Lane Reductions to facilitate Civil Road Work at the South East Corner of Pharmacy Intersection

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing civil road work activities along Eglinton Avenue East. Starting as early as Monday, March 18 and lasting for approximately twelve (12) days, crews will be conducting curb installation at the south-east corner of Pharmacy Avenue and Eglinton Avenue East. 

In order to facilitate this work, there will be temporary lane reduction at the south east corner of Pharmacy Avenue.  Read more »

March 132019

Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue.  Read more »

March 072019

Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

February 282019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

February 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Read more »

February 192019

Overnight Temporary Traffic Diversion to Facilitate Sub-Surface Infrastructure for Future Traffic Signals at Eglinton Square

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be installing the conduits for the permanent traffic signals at Eglinton Square. Starting as early as Wednesday, February 20, 2019 until Thursday, February 21, 2019. The work will taking place during the overnight period. Read more »

February 122019

Sidewalk Closure between Pharmacy and Lebovic for Civil Road Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue.

There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work, beginning as early as Monday February 18, 2019 for approximately one (1) month. Read more »

February 052019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »