What's New?

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
Syndicate content
 
January 31 2020

Upcoming Concrete Pour at Mount Pleasant Station Wednesday, February 5, 2020

 

What Work is Taking Place?

As early as Wednesday, February 5, 2020, crews will perform a concrete pour in the north work zone at Mount Pleasant Road and Eglinton Avenue East.  The concrete will form part of the roof of Mount Pleasant Station. Two concrete pumps will be set up within the work zone. Read more »

January 31 2020

TPSS 11 Utility Work at Warden Avenue and Eglinton Avenue East - February 3 – February 7, 2020

 

What Work is Taking Place

As part of the ongoing construction to support the future surface alignment for the Eglinton Crosstown LRT, lanes will be restricted at Warden Avenue to raise the existing maintenance holes to street level. Work will begin as early as Monday, February 3, 2020 and last for five (5) days.

Northbound and southbound lanes will be restricted on Warden Avenue at Eglinton Avenue East.

Work will include minor excavation, utility and grading work to raise the maintenance holes to ground level.

  Read more »

January 30 2020

Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020

The construction liaison committee meeting of Cedarvale & Forest Hill was held on January 29, 2020. You can view the presentation here:


Read more »

January 29 2020

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on January 28, 2020. You can see the presentation here:

 

Download the presentation

January 28 2020

Temporary Pedestrian Detour at Bayview Avenue and Eglinton Avenue East

Temporary Pedestrian Detour at Bayview Avenue and Eglinton Avenue East

  Read more »

January 28 2020

Upcoming Concrete Pour at Mount Pleasant Station - Saturday, February 1, 2020

 

What Work is Taking Place?

As early as Saturday February 1, 2020, crews will perform a concrete pour in the northeast work zone at Mount Pleasant Road and Eglinton Avenue East.  The concrete will form part of the roof of Mount Pleasant Station. Two concrete pumps will be set up within the work zone. Read more »

January 28 2020

Decking Removal at Science Centre Station

DECKING REMOVAL AT SCIENCE CENTRE STATION

DON MILLS ROAD AND EGLINTON AVENUE EAST Read more »

January 27 2020

OVERNIGHT INSTALLATION OF TEMPORARY POWER AT CHAPLIN STATION

What work is taking place?

As early as Monday, January 27, crews at Chaplin station will be working in the station’s future Main Entrance to install temporary power lines. Work will be ongoing from 7:00 p.m. until 5:00 a.m. Monday to Friday. Work involves the use of an excavator, concrete works, and the use of machinery for temporary power installation. Work does not involve heavy vibrations or noise. From 7:00 p.m. until 11:00 p.m., crews will be using a hydrovac. Noise can be expected.

 

Hours of Work Read more »