Road Resurfacing at Don Mills & Eglinton

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
May 1, 2019

UPDATE: NEW DATES

Due to the heavy precipitation experienced last week, the start date for overnight resurfacing work has been pushed back by one (1) day. The work is now scheduled for May 8-10. 

ORIGINAL POST: May 1, 2019

WHAT WORK IS TAKING PLACE?

At Science Centre Station, crews will be resurfacing the intersection at Don Mills Road and Eglinton Avenue East to improve the uneven road surface accrued during construction and the winter season. Milling and paving activities will occur overnight to minimize traffic impacts and begin as early as 7 p.m. on May 7, 2019. Work will occur between the hours of 7 p.m. - 6 a.m. May 8-10, 2019. There will be temporary changes to the traffic configuration (depicted below).  Traffic will revert to the current configuration each day.  

TIMING

Work will occur overnight between the hours of 7:00 p.m. and 6:00 a.m. May 8-10 , 2019.

Work may be rescheduled due to weather conditions or unforeseen circumstances.

  • May 8: Stage 1 and 2
  • May 9: Stage 3 and 4
  • May 10: Stage 1 and 2

TRAFFIC IMPACTS

  • Lane restrictions are required to complete resurfacing activities.
  • Road users can expect delays when travelling through the work zone.

PEDESTRIAN IMPACTS

  • Intermittent crosswalk closures will be required for the safety of pedestrians.
  • A minimum of three crosswalks will be maintained and signage will be installed directing pedestrians to available crosswalks.
  • Paid Duty Officers and/or flag person will be onsite overnight to assist in directing traffic and pedestrians.