July 17 2018

Construction Notice - Tentative Overnight Work at Mount Pleasant Station - July 19, 2018

Planned Overnight Work at Mount Pleasant Station

Thursday July 19, 2018*

 

 What Work is Taking Place?

On Thursday July 19, 2018 from 8:00 p.m. overnight to Friday morning at 6:00 a.m. Eglinton Avenue will be reduced to one shared lane of traffic between Mt. Pleasant Road westward toward Brownlow Avenue Read more »

July 13 2018

Construction Notice: Support of Excavation at Mount Pleasant Station

 

Support of Excavation at Mount Pleasant Station  

 

What Work is Taking Place? Read more »

July 12 2018

Update: Resumption of Overnight Utility Relocation Work on Transway Crescent for the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will resume relocating watermain and sanitary utilities on Transway Crescent, starting as soon as July 15, 2018.

To reduce impacts to the community and commuters this work will be performed overnight and will take approximately three (3) weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT.

Stage 3 Read more »

July 12 2018

Leaside - Laird Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on July 11, 2018. You can see the presentation here:

Read more »

July 10 2018
July 09 2018

OVERNIGHT WATER MAIN TESTING LAIRD STATION

OVERNIGHT WATER MAIN TESTING

LAIRD STATION

On Wednesday, July 11, crews will test local watermains along Eglinton Avenue East from Brentcliffe Drive to Sutherland Drive. Periodic testing of utilities during the mining operations ensures work continues safely.

TIMING  Read more »

July 06 2018

Toronto Hydro Work Relocation across Yonge Street

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews will begin the next phase of re-routing existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.  

For this next stretch of the work, crews will be working to install new Toronto Hydro infrastructure within the City of Toronto’s public right-of-way across Yonge Street. Crews may use a hydro-vacuum truck, excavators, jack-hammer and other construction equipment to complete the work. Read more »

July 06 2018

Support of Excavation Works at the North End of Kennedy GO Station Platform as Part of Eglinton Crosstown LRT

What Work is Taking Place?

As part of construction of the future Eglinton Crosstown LRT, improvements are also being made to the GO Transit Stouffville Corridor at Kennedy GO Station. Improvements include building a new west platform; rebuilding the existing east platform; constructing a new ticketing building for the GO Station; and building a new south pedestrian underpass. Read more »

July 06 2018

UPDATE: Upcoming Traffic & Pedestrian Changes at Eglinton Station

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring at the TTC bus depot and along south side of Eglinton has been complete. The work is carried out along the north side of Eglinton.

The next phase (depicted below) will take approximately 2-3 months to complete. The entire shoring process will take approximately twenty-four (24) months to complete. Read more »